Skip to main content

MPXJ

MPXJ is a Java library which allows a variety of project file formats and databases to be read and written. This Python package uses the JPype Java bridge to allow direct access from Python to the MPXJ library. You can find details of the Java classes and methods in the Javadocs, and more general documentation on the MPXJ website.

After installing this package you can either work with some of the simple built-in utilities provided by MPXJ for tasks like file format conversion:

import jpype
import mpxj

jpype.startJVM()
from org.mpxj.sample import MpxjConvert
MpxjConvert().process('example.mpp', 'example.mpx')
jpype.shutdownJVM()

or you can interact directly with the object model exposed by MPXJ to extract data:

import jpype
import mpxj

jpype.startJVM()
from org.mpxj.reader import UniversalProjectReader
project = UniversalProjectReader().read('example.mpp')

print("Tasks")
for task in project.getTasks():
	print(task.getID().toString() + "\t" + task.getName())

jpype.shutdownJVM()

or finally you can generate your own schedule:

import jpype
import mpxj

jpype.startJVM()

from java.lang import Double
from java.time import LocalDate, LocalDateTime
from org.mpxj import ProjectFile, TaskField, Duration, TimeUnit, RelationType, Availability, Relation
from org.mpxj.common import LocalDateTimeHelper
from org.mpxj.writer import UniversalProjectWriter, FileFormat

# The helper class we use later to actually write the file
# uses an enumeration to determine the output format.
file_name = "test.xml"
file_format = FileFormat.MSPDI

# Create a ProjectFile instance
file = ProjectFile()

# Add a default calendar called "Standard"
calendar = file.addDefaultBaseCalendar()

# Add a holiday to the calendar to demonstrate calendar exceptions
calendar.addCalendarException(LocalDate.of(2006, 3, 13), LocalDate.of(2006, 3, 13))

# Retrieve the project properties and set the start date. Note Microsoft
# Project appears to reset all task dates relative to this date, so this
# date must match the start date of the earliest task for you to see
# the expected results. If this value is not set, it will default to
# today's date.
properties = file.getProjectProperties()
properties.setStartDate(LocalDateTime.of(2003, 1, 1, 8, 0))

# Set a couple more properties just for fun
properties.setProjectTitle("Created by MPXJ")
properties.setAuthor("Jon Iles")

# Let's create an alias for TEXT1
customFields = file.getCustomFields()
field = customFields.getOrCreate(TaskField.TEXT1)
field.setAlias("My Custom Field")

# Add resources
resource1 = file.addResource()
resource1.setName("Resource1")

resource2 = file.addResource()
resource2.setName("Resource2")
# This resource is only available 50% of the time
resource2.getAvailability().add(Availability(LocalDateTimeHelper.START_DATE_NA, LocalDateTimeHelper.END_DATE_NA, Double.valueOf(50.0)));


# Create a summary task
task1 = file.addTask()
task1.setName("Summary Task")

# Create the first sub task
task2 = task1.addTask()
task2.setName("First Sub Task")
task2.setDuration(Duration.getInstance(10.5, TimeUnit.DAYS))
task2.setStart(LocalDateTime.of(2003, 1, 1, 8, 0))
task2.setText(1, "My Custom Value 1")

# We'll set this task up as being 50% complete. If we have no resource
# assignments for this task, this is enough information for MS Project.
# If we do have resource assignments, the assignment record needs to
# contain the corresponding work and actual work fields set to the
# correct values in order for MS project to mark the task as complete
# or partially complete.
task2.setPercentageComplete(Double.valueOf(50.0))
task2.setActualStart(LocalDateTime.of(2003, 1, 1, 8, 0))

# Create the second sub task
task3 = task1.addTask()
task3.setName("Second Sub Task")
task3.setStart(LocalDateTime.of(2003, 1, 11, 8, 0))
task3.setDuration(Duration.getInstance(10, TimeUnit.DAYS))
task3.setText(1, "My Custom Value 2")


# Link these two tasks
task3.addPredecessor(Relation.Builder().targetTask(task2))

# Add a milestone
milestone1 = task1.addTask()
milestone1.setName("Milestone")
milestone1.setStart(LocalDateTime.of(2003, 1, 21, 8, 0))
milestone1.setDuration(Duration.getInstance(0, TimeUnit.DAYS))
milestone1.addPredecessor(Relation.Builder().targetTask(task3))

# This final task has a percent complete value, but no
# resource assignments. This is an interesting case it it requires
# special processing to generate the MSPDI file correctly.
task4 = file.addTask()
task4.setName("Next Task")
task4.setDuration(Duration.getInstance(8, TimeUnit.DAYS))
task4.setStart(LocalDateTime.of(2003, 1, 1, 8, 0))
task4.setPercentageComplete(Double.valueOf(70.0))
task4.setActualStart(LocalDateTime.of(2003, 1, 1, 8, 0))

# Assign resources to tasks
assignment1 = task2.addResourceAssignment(resource1)
assignment2 = task3.addResourceAssignment(resource2)

# As the first task is partially complete, and we are adding
# a resource assignment, we must set the work and actual work
# fields in the assignment to appropriate values, or MS Project
# won't recognise the task as being complete or partially complete
assignment1.setWork(Duration.getInstance(80, TimeUnit.HOURS))
assignment1.setActualWork(Duration.getInstance(40, TimeUnit.HOURS))

# If we were just generating an MPX file, we would already have enough
# attributes set to create the file correctly. If we want to generate
# an MSPDI file, we must also set the assignment start dates and
# the remaining work attribute. The assignment start dates will normally
# be the same as the task start dates.
assignment1.setRemainingWork(Duration.getInstance(40, TimeUnit.HOURS))
assignment2.setRemainingWork(Duration.getInstance(80, TimeUnit.HOURS))
assignment1.setStart(LocalDateTime.of(2003, 1, 1, 8, 0))
assignment2.setStart(LocalDateTime.of(2003, 1, 11, 8, 0))

# Write a 100% complete task
task5 = file.addTask()
task5.setName("Last Task")
task5.setDuration(Duration.getInstance(3, TimeUnit.DAYS))
task5.setStart(LocalDateTime.of(2003, 1, 1, 8, 0))
task5.setPercentageComplete(Double.valueOf(100.0))
task5.setActualStart(LocalDateTime.of(2003, 1, 1, 8, 0))

# Write a 100% complete milestone
task6 = file.addTask()
task6.setName("Last Milestone")
task6.setDuration(Duration.getInstance(0, TimeUnit.DAYS))
task6.setStart(LocalDateTime.of(2003, 1, 1, 8, 0))
task6.setPercentageComplete(Double.valueOf(100.0))
task6.setActualStart(LocalDateTime.of(2003, 1, 1, 8, 0))

# Write the file
writer = UniversalProjectWriter(file_format).write(file, file_name)

jpype.shutdownJVM()

Download files

Download the file for your platform. If you're not sure which to choose, learn more about installing packages.

Source Distribution

mpxj-16.6.0.tar.gz (31.3 MB view details)

Uploaded Source

Built Distribution

If you're not sure about the file name format, learn more about wheel file names.

mpxj-16.6.0-py3-none-any.whl (31.3 MB view details)

Uploaded Python 3

File details

Details for the file mpxj-16.6.0.tar.gz.

File metadata

  • Download URL: mpxj-16.6.0.tar.gz
  • Upload date:
  • Size: 31.3 MB
  • Tags: Source
  • Uploaded using Trusted Publishing? No
  • Uploaded via: twine/6.1.0 CPython/3.11.9

File hashes

Hashes for mpxj-16.6.0.tar.gz
Algorithm Hash digest
SHA256 927a0189ef6dc5ca328653f9253879d653e17a78bf9fd6bbb2233eefc8308257
MD5 461456940681cd2fca700dc93a9a7309
BLAKE2b-256 f98632145290ab10c4733cce345bf3de9d68560903ad97ff4f75677a4037cce1

See more details on using hashes here.

File details

Details for the file mpxj-16.6.0-py3-none-any.whl.

File metadata

  • Download URL: mpxj-16.6.0-py3-none-any.whl
  • Upload date:
  • Size: 31.3 MB
  • Tags: Python 3
  • Uploaded using Trusted Publishing? No
  • Uploaded via: twine/6.1.0 CPython/3.11.9

File hashes

Hashes for mpxj-16.6.0-py3-none-any.whl
Algorithm Hash digest
SHA256 51bd687a5677979d621c08b178dad93a36f0d1601c454dadf7ad85647b50f3fb
MD5 b89eed4d6968c48eebac9d20a2ad4db8
BLAKE2b-256 49844d114fb70b0ec4ae71daa7deb603fa44119277df6f04c5bae3e41b75abad

See more details on using hashes here.

Release history Release notifications | RSS feed

Supported by

AWS Cloud computing and Security Sponsor Datadog Monitoring Depot Continuous Integration Fastly CDN Google Download Analytics Pingdom Monitoring Sentry Error logging StatusPage Status page