Adds an MRP Scheduler

Project description

Beta License: LGPL-3 OCA/manufacture Translate me on Weblate Try me on Runbot

This module allows you to calculate, based in known inventory, demand, and supply, and based on parameters set at product variant level, the new procurements for each product.

To do this, the calculation starts at top level of the bill of material and explodes this down to the lowest level.

Key Features

  • MRP parameters set by product variant MRP area pairs.

  • Cron job to calculate the MRP demand.

  • Manually calculate the MRP demand.

  • Confirm the calculated MRP demand and create PO’s, or MO’s.

  • Able to see the products for which action is needed throught Planned Orders.

  • Integration with Stock Demand Estimates system. Note: You need to install mrp_multi_level_estimate module.

Table of contents

Configuration

MRP Areas

  • Go to Manufacturing > Configuration > MRP Areas and define or edit any existing area. You can specify the working hours for every area.

Product MRP Area Parameters

  • Go to Manufacturing > Master Data > Product MRP Area Parameters and set the MRP parameters for a given product and area.

Usage

To manually run the MRP scheduler:

  1. Go to Manufacturing > Operations > Run MRP Multi Level.

  2. On the wizard click Run MRP.

To launch replenishment orders (moves, purchases, production orders…):

  1. Go to Manufacturing > Operations > MRP Inventory.

  2. Filter with To procure.

  3. Select multiple records and click on Action > Procure or click the right hand side gears in any record.

  4. On the wizard, check everything is ok and click Execute.

Changelog

12.0.2.1.0 (2020-04-09)

Features

  • Show Run MRP Multi Level menu only to a specific new security group Run MRP Manually. (#492)

12.0.2.0.0 (2020-03-31)

  • Improving the management of planned orders:

    • Add menu entry for planned orders

    • Add button to navigate from planned orders to linked manufacturing orders

    • Add action to convert planned orders to fixed

    • When changing the due date in a planned order the release date is recomputed

  • [IMP] Minor changes” (#470).

    • Planned Order release and due date become required.

    • Add button to Product MRP Area to update MOQ from Supplier Info.

    • Link Manufacturing Orders with Planned Orders.

    • Allow Mrp Inventory Procure Wizard to be used from other models.

    • Make MRP Inventory creation more extensible.

    • Main Supplier computation (v13 requires explicit False definitions)

  • [IMP] Minor changes (#468).

    • Planned Orders become fixed on manual creation by default

    • Released Quantity becomes readonly

    • Add product reference if Planned Order name is not defined on bom explosion

  • [FIX] Minor changes (#469).

    • Fix Main supplier computation in multi company

    • Drop Triplicated field in search view

  • [IMP] Minor changes (#463).

    • Show supply method on MRP Inventory

    • Allow no-MRP users to look into Products

12.0.1.0.0 (2019-08-05)

  • [MIG] Migration to v12:

    • Estimates as a forecasting mechanism is moved to a new module (mrp_multi_level_estimate).

11.0.3.0.0 (2019-05-22)

  • [REW/IMP] Rework to include Planned Orders. (#365).

  • [IMP] Able to procure from a different location than the area’s location.

11.0.2.2.0 (2019-05-02)

  • [IMP] Able to run MRP only for selected areas. (#360).

11.0.2.1.0 (2019-04-02)

  • [IMP] Implement Nbr. Days functionality to be able to group demand when generating supply proposals. (#345).

11.0.2.0.0 (2018-11-20)

  • [REW] Refactor MRP Area. (#322):

    • MRP product concept dropped in favor of Product MRP Area Parameters. This allow to set different MRP parameters for the same product in different areas.

    • Menu items reordering.

11.0.1.1.0 (2018-08-30)

  • [FIX] Consider Qty Multiple on product to propose the quantity to procure. (#297)

11.0.1.0.1 (2018-08-03)

  • [FIX] User and system locales doesn’t break MRP calculation. (#290)

  • [FIX] Working Hours are now defined only at Warehouse level and displayed as a related on MRP Areas. (#290)

11.0.1.0.0 (2018-07-09)

  • Start of the history.

Bug Tracker

Bugs are tracked on GitHub Issues. In case of trouble, please check there if your issue has already been reported. If you spotted it first, help us smashing it by providing a detailed and welcomed feedback.

Do not contact contributors directly about support or help with technical issues.

Credits

Authors

  • Ucamco

  • ForgeFlow

Contributors

Maintainers

This module is maintained by the OCA.

Odoo Community Association

OCA, or the Odoo Community Association, is a nonprofit organization whose mission is to support the collaborative development of Odoo features and promote its widespread use.

Current maintainers:

JordiBForgeFlow LoisRForgeFlow

This module is part of the OCA/manufacture project on GitHub.

You are welcome to contribute. To learn how please visit https://odoo-community.org/page/Contribute.

Project details


Release history Release notifications | RSS feed

Download files

Download the file for your platform. If you're not sure which to choose, learn more about installing packages.

Source Distributions

No source distribution files available for this release.See tutorial on generating distribution archives.

Built Distribution

File details

Details for the file odoo12_addon_mrp_multi_level-12.0.2.4.1-py3-none-any.whl.

File metadata

File hashes

Hashes for odoo12_addon_mrp_multi_level-12.0.2.4.1-py3-none-any.whl
Algorithm Hash digest
SHA256 a64188727e6d6fe4377e96027fab418cb349937d4a013c9792d39a10effeef7b
MD5 2ca4bb1bda4d0d9a1c89e13e46c4e7a6
BLAKE2b-256 f1289078a019eeaa71129ee3831992b00e4f61730f06b3c17823443ba4d9d82f

See more details on using hashes here.

Supported by

AWS AWS Cloud computing and Security Sponsor Datadog Datadog Monitoring Fastly Fastly CDN Google Google Download Analytics Microsoft Microsoft PSF Sponsor Pingdom Pingdom Monitoring Sentry Sentry Error logging StatusPage StatusPage Status page