planwright

A maker of plans. Keep your plan as a plain Markdown table; planwright tells you the three things a project manager actually needs to know:

  • what is ready to start now,
  • what can run in parallel,
  • what the critical path is (the floor on how long the remaining work can take).

The plan is data — a Markdown file in git. The engine is deterministic and has zero runtime dependencies. And a Claude Code hook keeps the plan honest: it refuses to let the plan drift into a cycle or a dangling dependency.

Use it as a Python CLI, as a library, or as a Claude Code plugin (slash commands + a planning skill + the hook). It is built to plug into any project or agent and get out of the way.


Why it exists

Most "project-manager" agents are a prompt persona: they write a nice plan and then forget everything — no source of truth, no enforcement, so the work drifts back into a pile. planwright inverts that. The plan lives in a file you own, the schedule is computed from facts (not guessed by a model), and the discipline is enforced by a hook rather than good intentions. See POSITIONING.md.

Install

pip install planwright          # the CLI + library

Or use it straight from a checkout with no install:

PYTHONPATH=src python3 -m planwright.cli graph PLAN.md

The plan file

A plain GitHub-flavoured Markdown table. ID and Title are the only required columns; the rest are optional. Headers are case-insensitive and accept aliases (including Portuguese), so planwright reads a plan written in your own words.

| ID | Title                      | Status | Owner | Est  | Depends | Track |
|----|----------------------------|--------|-------|------|---------|-------|
| A1 | Design the data model      | done   | ana   | 1d   | -       | core  |
| A2 | Build the parser           | doing  | ana   | 2d   | A1      | core  |
| A3 | Build the dependency graph | todo   | luis  | 2d   | A1      | core  |
| A4 | Wire the CLI               | todo   | ana   | 1d   | A2, A3  | core  |
| B1 | Write the README           | todo   | bea   | 0.5d | -       | docs  |
  • Status: todo · doing · blocked · done (aliases: open/aberto, wip/em curso, bloqueado, fechado, …).
  • Est: a size S/M/L/XL, or a duration 2h / 3d / 1w; - = not sized yet.
  • Depends: ids this item waits on (comma/space separated); - = none.
  • Track: any label to group items (a feature, a workstream, a phase).

The table can live inside a larger document — planwright reads the first table that has ID and Title and ignores everything else.

Commands

planwright graph    PLAN.md          # ready now · parallel layers · blocked · critical path
planwright action   PLAN.md          # a manager's action plan: ranked ready, who-unblocks-what, critical
planwright mermaid  PLAN.md          # Mermaid diagrams (deps + Kanban board) — render in GitHub/Markdown
planwright next     PLAN.md          # just the ids ready to start now (one per line)
planwright export   PLAN.md          # emit the stable JSON contract for an execution runner
planwright validate PLAN.md [--strict]  # check the plan is sound (and disciplined)
planwright status   PLAN.md          # one-line status counts

graph/next/status take --json; mermaid takes --view deps|board|all. The path defaults to PLAN.md (override with $PLANWRIGHT_PLAN).

See it, don't read it

planwright mermaid emits mermaid blocks that render natively on GitHub, so a manager sees the dependency graph (coloured by status) and a Kanban board without reading the CLI. planwright action ranks what to start now by leverage: human decisions that unblock others first, then the critical path, then the rest.

Hand-off to an execution runner

planwright export PLAN.md emits a stable, versioned JSON contract (planwright-plan/v1) — the clean boundary between planning (planwright) and execution (a runner). planwright describes the plan; a runner imports it, authorizes, runs, and records. autonomy/complexity travel as signals for the runner's selection logic, never as runtime policy, and planwright holds no authz/budget/tools/events. See the monorepo's docs/architecture/PLAN-CONTRACT.md.

Optional columns (for routing)

Two optional columns feed autonomy/complexity-aware routing; absent, they are ignored:

  • Autonomy — auto (an agent can close it) · assisted · human (needs a person).
  • Complexity — C1..C4 (cognitive risk, for cheap→expensive model routing), independent of Est (effort). A task can be Est=S and C4.

Example:

$ planwright graph PLAN.md
plan: 5 items  (todo 3, doing 1, blocked 0, done 1)

READY NOW (3): start these today
  A2  Build the parser  (2d @ana)
  A3  Build the dependency graph  (2d @luis)
  B1  Write the README  (4h @bea)

PARALLEL LAYERS (2): each layer can run at once
  L0: A2, A3, B1
  L1: A4

CRITICAL PATH: 4d — A1 -> A2 -> A4
  (the floor on remaining time; shortening the plan means shortening this)

As a Claude Code plugin

planwright is also a plugin. Load it straight from a checkout:

claude --plugin-dir oss/planwright          # from the monorepo root
# or, once published as its own repo / marketplace:
# /plugin install planwright --marketplace <owner>/<repo>

You then get:

  • /planwright:plan-status — the schedule, summarised.
  • /planwright:plan-new — start a plan or add an item through the method.
  • /planwright:plan-triage — sort a crowded backlog into real vs. resolvable vs. stale.
  • the governed-planning skill — the five-gate method (idea → research → spec → WBS → execute) and the one rule (nothing starts without an estimate and explicit dependencies).
  • a PostToolUse hook — after any edit to a plan file (PLAN.md or *.plan.md), it validates and blocks on an unsound schedule so the plan never silently rots. Set PLANWRIGHT_STRICT=1 to also block on governance warnings.

Validation rules

Errors (not a sound schedule — fix before trusting the graph): a parse failure, a duplicate id, a dependency naming no item, a self-dependency, a cycle.

Warnings (schedulable but undisciplined; --strict turns these into failures): an item marked doing/done with no estimate; a done item that still depends on unfinished work.

Library

from planwright.parse import parse_plan
from planwright.graph import Graph

plan = parse_plan("PLAN.md")
g = Graph(plan)
print([i.id for i in g.ready()])      # ready now
print(g.parallel_layers())            # [[...], [...]]
print(g.critical_path().hours)        # float (hours)

Part of a proven composition (the accountability layer)

planwright describes and prioritizes; it does not execute. Paired with an execution runner it becomes an accountability layer for agent work: a plan that cannot silently rot, handed to a runner that gates, budgets and verifies. The hand-off is a thin, versioned contract — and the whole path is proven by tests, not asserted:

  • the contract (planwright export → a runner imports it): monorepo docs/architecture/PLAN-CONTRACT.md;
  • the canonical scenario — one run with a human gate, a budget cap and completion checked by evidence: docs/architecture/CANONICAL-SCENARIO.md;
  • where it fits vs. frameworks and persona collections: docs/initiatives/COMPETITIVE-ANALYSIS.md.

The signals planwright exports (Autonomy/Complexity) travel as planning intent, never as runtime policy — the runner stays the authority at runtime.

License

MIT. No third-party runtime dependencies. See LICENSE and NOTICE.

Metadata

Release files for planwright 0.3.0

For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.

Source distribution (sdist)

Source distribution for planwright 0.3.0
File Size Uploaded
planwright-0.3.0.tar.gz 28.7 kB Details

Built distribution (wheel)

Table of built distributions (wheels) for planwright 0.3.0
File Interpreter ABI Platform
planwright-0.3.0-py3-none-any.whl Python 3 none any Details

Total release size: 52.3 kB

Release files / planwright-0.3.0.tar.gz

Download URL planwright-0.3.0.tar.gz
Size 28.7 kB
Tags Source
SHA-256 checksum
How to use checksums
9fe79523814e34b22721f01bc0df9d8dc64d92d626b69c3964a1d6f7797b2b5d
BLAKE2b-256 checksum
How to use checksums
f4dd869f04e96cc090b7d411345d783b4cc59aa4c67b5213a6e1f0352fef909c
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
Yes
Uploaded via twine/7.0.0 CPython/3.13.14

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

PyPI Publish Attestation

PyPI verified that this artifact, at this checksum, originated from the publisher listed below.

Signed by GitHub Actions, verified by PyPI on Oct 10, 2026.

Transparency log

Release files / planwright-0.3.0-py3-none-any.whl

Download URL planwright-0.3.0-py3-none-any.whl
Size 23.6 kB
Tags Python 3
SHA-256 checksum
How to use checksums
81de196c8bd9e7c3408fd665b041bc4cccfa60622423db759c22e297f0e5495a
BLAKE2b-256 checksum
How to use checksums
02122f124b8a360da79ee1b5f9b4a36f5063ae1002273d9f65ba52d4241c23d0
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
Yes
Uploaded via twine/7.0.0 CPython/3.13.14

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

PyPI Publish Attestation

PyPI verified that this artifact, at this checksum, originated from the publisher listed below.

Signed by GitHub Actions, verified by PyPI on Oct 10, 2026.

Transparency log

Release history Release notifications | RSS feed

0.4.0

2 release files

This release

0.3.0 This release

2 release files

Anthropic, PBC Visionary sponsor Bloomberg Visionary sponsor Hudson River Trading Visionary sponsor Meta Visionary sponsor NVIDIA Visionary sponsor Microsoft Sustainability sponsor Depot Continuous Integration AWS Cloud computing and Security Sponsor Datadog Monitoring Fastly CDN Google Download Analytics Sentry Error logging StatusPage Status page