ScriptPlan

ScriptPlan

Tests Probes Python Licence

A precise project scheduling engine with minute-level accuracy for resource allocation and dependency management. It reads projects written in the .tjp format.

Installation

pip install scriptplan

Quick Start

Report Generation (Unix-style)

# Generate JSON report to stdout
plan report project.tjp

# Generate CSV report
plan report --csv project.tjp

# Save to file
plan report project.tjp > output.json
plan report --csv project.tjp > output.csv

# Read from stdin
cat project.tjp | plan report
plan report - < project.tjp

# Pipe to other tools
plan report project.tjp | jq '.data[0]'
plan report --csv project.tjp | csvkit

# Process multiple files
for f in projects/*.tjp; do
  plan report "$f" | jq -r '.report_id'
done

Output Format (JSON):

{
  "data": [
    {
      "id": "project.task1",
      "start": "2024-01-01-09:00",
      "end": "2024-01-05-17:00"
    }
  ],
  "columns": ["id", "start", "end"],
  "report_id": "ea3f901dd6426dfa58288d945819c75485fd9ff1875db59def350f219e2d62ca"
}

Features:

  • Output to stdout (Unix philosophy)
  • Messages to stderr
  • SHA256 report_id over the rendered result, so it changes when the schedule does
  • Lowercase column names
  • No HTML metadata
  • No file pollution (uses temp directories)
  • Separate processes do not collide: temporary files and directories are unique per run

Python API

from scriptplan.parser.tjp_parser import ProjectFileParser

parser = ProjectFileParser()
project = parser.parse(open('project.tjp').read())

# Access scheduled tasks
for task in project.tasks:
    if task.leaf():
        start = task.get('start', 0)
        end = task.get('end', 0)
        print(f"{task.id}: {start} -> {end}")

Projects can be parsed and scheduled in parallel threads. Messages and the error count belong to the thread that produced them, so read get_message_handler_instance().messages in the thread that called schedule().

What is verified

Each behaviour below has a probe in audit/evaluations/ that drives ScriptPlan through its own API or CLI and asserts the result. They run as part of the test suite, and can be run on their own against an installed release:

audit/evaluations/run_all.sh

Time

  • Dates are read in the project's timezone and scheduled in UTC; reports convert back.
  • Resource shifts follow their own timezone across daylight-saving changes in both directions.
  • A working-hours interval that crosses midnight applies to the following day.
  • The project's workinghours is the calendar that length, gaplength and a resource with no hours of its own use. Without one it is Monday to Friday, 09:00-17:00, in the project's timezone.
  • A global leaves or vacation closes that calendar for everyone, whatever the leave is called, for whole days or part of one. A shift's leaves holds for every resource on the shift.
  • Slot size is derived from the times a project uses, so start 09:30 is honoured exactly and a shift of 08:13 - 11:59, 13:07 - 17:47 yields its true 8h26m a day. timingresolution overrides this.

Units

  • Calendar time (duration, gapduration) and working time (effort, length, gaplength) are distinguished, with working time derived from dailyworkinghours and yearlyworkingdays. m means months; min means minutes.

Resources

  • effort is person-time: two resources available in a slot contribute two slots of it. mandatory requires a resource for the task to progress at all; persistent keeps the one first chosen; alternative falls back.
  • Allocating a resource that has members allocates every member.
  • A task with a duration, or with a stated start and end, books the resources it allocates for the hours they are on shift and free. It keeps its dates when they are not.
  • dailymax, weeklymax, monthlymax and maximum block at the cap and release in the next period. Periods are counted in the resource's own calendar, a week runs Monday to Sunday, and a cap smaller than one slot is honoured exactly.
  • dailymin, weeklymin, monthlymin and minimum are targets, which placing tasks cannot guarantee. A period in which the resource or task was booked for less draws a warning once the schedule is complete.

Scheduling

  • ASAP and ALAP, including chains that mix the two.
  • A task scheduled as late as possible ends by the earliest of its own end, the start of each successor (less any gap that successor asks for) and the project end. With none of these but a successor scheduled as soon as possible that states no start, it is scheduled as soon as possible instead, with a warning.
  • Contention is resolved by priority, then criticalness, then declaration order. A task's criticalness is its effort times how much is asked of the resources it may use, plus that of the heaviest chain of tasks that follow it, so at equal priority the larger effort is placed first. Tasks are placed one at a time in that order, so a task ranked higher takes a resource's daily or weekly allowance first, and a lower-ranked task that started earlier can finish later. Raising its priority keeps it going.
  • The declared project period is never rewritten. A task that does not fit is reported, with its name and the reason. A date stated outside the period is an error.
  • Scheduling the same project twice produces the same dates and the same bookings.
  • A stated start or end that the schedule cannot keep, and a task that would start before something it depends on finishes, are errors.
  • length and gaplength count the project's working time, not a resource's: a resource on longer hours does not shorten the gap.
  • maxgapduration, maxstart, minstart, maxend and minend are checked once the schedule is complete, and a violation is an error. (maxgaplength is not part of the syntax and is refused when parsed.)

Honesty

  • A project that cannot be scheduled exits non-zero and says why. A dependency cycle is rejected before scheduling, naming the cycle.
  • An attribute or reference the parser cannot place is an error, never a silent drop. Each directive the grammar accepts has a probe showing that it changes a schedule, is refused or draws a warning, and the few that do none of these are listed in audit/evaluations/probe_directive_effect.py with the reason.
  • Warnings are printed to stderr by plan report as well as by scriptplan.
  • report_id is a SHA-256 of the rendered result, so it differs when the schedule differs.

Known limits

  • include, supplement, leaveallowance and statussheet are not implemented.
  • Output formats are JSON and CSV. ical, tjp, niku and MS Project XML are rejected at parse time rather than silently producing nothing.
  • Accounts are parsed but not yet modelled, so chargeset and charge record an amount without posting it anywhere.
  • The value a task or resource gives to a custom attribute declared with extend is read and not kept.
  • limits inside an allocate option block is refused. Put the limits on the task, with { resources <id> } to hold them to one resource.
  • The workinghours lines of one block (project, shift or resource) state its whole week: a day no line names is not worked, and two lines naming the same day add up. Other schedulers of this format keep the inherited hours on a day a line does not name. Name every day you mean.
  • A length task with no start of its own is reported as starting at the first working moment it can, where other schedulers report the moment it was released, which may be midnight. The end is the same.
  • Each resource holds one entry per slot for the whole project, so memory grows with resources times the project's length divided by the slot size. Times off the hour make the slots smaller; timingresolution sets the size outright.
  • A task reference is looked up from the referring task's scope, one level up for each !. When the !s stop at a task, the reference must name one of its children: !x with no sibling x is refused. When there are no !s, or they reach the top level of the project and no top-level task matches, the reference binds to the only task in the project with that id, so depends !!pack inside delivery finds delivery.pack. When two tasks could be meant, the file is refused and both are named.
  • onstart on a dependency means start-to-start for a task scheduled as soon as possible: it may start once the predecessor starts. For a task scheduled as late as possible it means the task must finish before the predecessor starts, which is ScriptPlan's own reading.

Example Project

project "Manufacturing" 2025-07-01 +1m {
  timezone "Etc/UTC"
  timeformat "%Y-%m-%d %H:%M"
  scheduling alap
}

shift factory_hours "Factory Hours" {
  workinghours mon - fri 08:00 - 16:00
}

resource machine "Press" {
  workinghours factory_hours
}

task delivery "Product Launch" {
  end 2025-07-18-16:00

  task pack "Packaging" {
    effort 8h
    allocate machine
  }

  task assemble_b "Body Assembly" {
    effort 16h
    allocate machine
    depends !!pack { onstart }
  }

  task assemble_a "Engine Assembly" {
    effort 16h
    allocate machine
  }
}

task connection_setup "Logic" {
  task set_deps "Apply" {
    depends !delivery.assemble_a, !delivery.assemble_b
    precedes !delivery.pack
  }
}

taskreport output "output" {
  formats csv
  columns id, start, end
  timeformat "%Y-%m-%d-%H:%M"
}

This project schedules backward from the delivery deadline (ALAP mode). The scheduler:

  1. Anchors packaging to end at 16:00 on July 18
  2. Schedules both assembly tasks to complete before packaging starts
  3. Resolves resource contention (single machine) by sequencing assemblies back-to-back
  4. Respects weekend boundaries (Mon-Fri working hours)

Result:

delivery.pack:       2025-07-18-08:00 -> 2025-07-18-16:00
delivery.assemble_a: 2025-07-14-08:00 -> 2025-07-15-16:00
delivery.assemble_b: 2025-07-16-08:00 -> 2025-07-17-16:00

License

Apache-2.0

Acknowledgments

ScriptPlan reads the .tjp project file format. It contains no code from any other scheduler: the parser, the scheduling algorithms and the reports are its own.

Why ScriptPlan?

This scheduler is part of Highway Workflow Engine's worker capacity management system. I decided to open-source it for the community to benefit from its precise scheduling capabilities. Because it reads the established .tjp syntax, users can adopt ScriptPlan without learning a new format.

Yours, Farshid.

Metadata

Release files for scriptplan 0.10.3

For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.

Source distribution (sdist)

Source distribution for scriptplan 0.10.3
File Size Uploaded Provenance Actions
scriptplan-0.10.3.tar.gz 316.9 kB Without provenance Details for scriptplan-0.10.3.tar.gz

Built distribution (wheel)

Table of built distributions (wheels) for scriptplan 0.10.3
File Interpreter ABI Platform Actions
scriptplan-0.10.3-py3-none-any.whl Python 3 none any Details for scriptplan-0.10.3-py3-none-any.whl

Total release size: 520.5 kB

Release files / scriptplan-0.10.3.tar.gz

Download URL scriptplan-0.10.3.tar.gz
Size 316.9 kB
Tags Source
SHA-256 checksum
How to use checksums
aabbcc042c826b7b2934550f9f8bbbd837f8553d1d4cfd02704919d826b02472
BLAKE2b-256 checksum
How to use checksums
d5d4a1abf270c61feb0c8f4347fc1a45c00ab5963fbb895b9611ebb34f10f9cd
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
No
Uploaded via twine/6.2.0 CPython/3.9.25

Release files / scriptplan-0.10.3-py3-none-any.whl

Download URL scriptplan-0.10.3-py3-none-any.whl
Size 203.6 kB
Tags Python 3
SHA-256 checksum
How to use checksums
76a9216ecbfe543076f174721f8a12f9194ea9aaef64e67504c33bf369ac1279
BLAKE2b-256 checksum
How to use checksums
08b052d07a32d5959e6c2f200034e2a72c9edc79e28ee7efd6a628a2b304125b
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
No
Uploaded via twine/6.2.0 CPython/3.9.25

Security for scriptplan 0.10.3

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

No provenance found

None of the files in this release were uploaded with provenance metadata.

A note on package security

PyPI is a repository for distributing packages, not a service for auditing them. While third-party security researchers and our staff do their best to detect and remove malicious packages, PyPI cannot guarantee the quality, security or suitability of any given package.

To learn more about protecting yourself from malicious actors, visit our package security documentation.

Anthropic, PBC Visionary sponsor Bloomberg Visionary sponsor Hudson River Trading Visionary sponsor Meta Visionary sponsor NVIDIA Visionary sponsor Microsoft Sustainability sponsor Depot Continuous Integration AWS Cloud computing and Security Sponsor Datadog Monitoring Fastly CDN Google Download Analytics Sentry Error logging StatusPage Status page