Project Planner

A small planning system that lets you define project plans and tasks in either YAML or Python.

A plan can include optional top-level project metadata:

  • portfolio: portfolio or parent program name.
  • project: high-level project name.
  • managers: list of manager names.
  • pocs: list of point-of-contact names.
  • summary: high-level plan summary.
  • fiscal_range_begin and fiscal_range_end: optional fiscal year range covered by the plan, for example 27 through 31.
  • execution: execution metadata. It can be a mapping with overview text and sections, where each section has label, description, and an optional stable id for task links. The older flat list of sections is still accepted.

Each task supports these fields:

  • id: required string task id. Must contain only letters, numbers, or underscores, with no spaces.
  • label: required string display name for the task.
  • site: optional site or institution label.
  • bnr: optional budget and reporting identifier.
  • cost: optional task cost label, for example $100K.
  • funding status or funding_status: optional funding state label.
  • type: optional task type label.
  • tags: optional comma-separated string or list of task tags.
  • project: required string project name.
  • execution_section: optional ID of a section under execution.sections. Linked tasks use that section's label and position for activity headings and task numbers in exports. An unknown ID is rejected.
  • description: required string describing the task.
  • notes: optional string with additional task notes.
  • start: required fiscal period string in M{month}Q{quarter}FY{year} format, where month is 1 to 3 within the quarter.
  • deadline: required fiscal period string in M{month}Q{quarter}FY{year} format, where month is 1 to 3 within the quarter.
  • completed: optional fiscal period string for work that is already complete. A task with status: complete and completed may omit planning-only fields: start, deadline, expected duration, milestone, priority, dependencies, and risk. Without completed, these fields are required.
  • expected duration or expected_duration: required positive whole number of months.
  • milestone: required string milestone name.
  • priority: required string priority label such as low, medium, high, or urgent.
  • status: required string status. Allowed values are pending, active, ongoing, blocked, unfunded, and complete. Set unfunded explicitly for work awaiting funding.
  • dependencies: required list of task ids. Each dependency must reference another task id.
  • risk: required risk entry or list of risk entries. Each entry has type, level, and mitigation, and may include description; level must be low, medium, high, or extreme.
  • funding: optional mapping of fiscal year to funding level, for example fy27: 50K. A task is treated as unfunded for fiscal years not present in this mapping.

A task can also be a multi-part task by using parts instead of the per-task schedule fields on the parent. Parent fields such as project, execution_section, site, bnr, notes, type, tags, and funding are inherited by each part, while each part provides its own id, label, description, start, deadline, expected duration, milestone, priority, status, dependencies, and risk. Part ids are expanded as {parent_id}_{part_id}. Dependencies inside a multi-part task can reference sibling part ids, and dependencies from other tasks can reference the parent id to depend on all expanded parts. Parent-level funding inherited by multiple parts is counted once in fiscal-year totals. In exports, parts in the same activity stay together at the position of their first part, and keep their order relative to one another.

Quick start

Run from this directory:

planner validate planner/examples/tasks.yaml
planner list planner/examples/tasks.yaml
planner list-detail planner/examples/tasks.yaml
planner summary planner/examples/tasks.yaml
planner schedule planner/examples/tasks.yaml
planner export planner/examples/tasks.yaml /tmp/plan.docx
planner export planner/examples/tasks.yaml /tmp/plan.svg
planner export-gantt planner/examples/tasks.yaml /tmp/gantt.svg
planner export-gantt planner/examples/tasks.yaml /tmp/gantt.pptx
planner export-gantt planner/examples/tasks.yaml /tmp/fy26-fy27.svg --from FY26 --through FY27
planner export-gantt planner/examples/tasks.yaml /tmp/partial.pptx --from M1Q1FY26 --through M3Q2FY27

If you set TUXFAN_PLANNER_DATAFILE, the CLI uses that file by default:

export TUXFAN_PLANNER_DATAFILE=planner/examples/tasks.yaml
planner validate
planner list
planner list-detail
planner export /tmp/plan.docx
planner export /tmp/plan.svg
planner export-gantt /tmp/gantt.pptx

If you set TUXFAN_PLANNER_EXPORT_OPTIONS, the Word and SVG plan exports use that file by default:

export TUXFAN_PLANNER_EXPORT_OPTIONS=planner/examples/export-options.yaml
planner export planner/examples/tasks.yaml /tmp/plan.docx

You can also install it locally:

python3 -m pip install -e .
planner list planner/examples/tasks.yaml

The legacy tuxfan-planner command remains available as an alias. Run planner --help to see the current values of both planner environment variables alongside the command help. Ill-formed commands print an error and the relevant help text to stderr, then exit with status 2.

Shell completion

The CLI can print completion scripts for bash, zsh, and fish:

planner completion bash
planner completion zsh
planner completion fish

For a one-session bash setup:

source <(planner completion bash)

The generated completion supports the basic planner subcommands, the tuxfan-planner alias, file path completion for task and output arguments, and --export-options for export commands. It also completes the list --color values.

Documentation

Sphinx documentation lives in docs/. See the developer setup and checks for the current dependency and HTML build commands.

On GitHub, the Documentation workflow builds the same Sphinx output and publishes it to the gh-pages branch. Configure the repository Pages settings to serve from the gh-pages branch root.

Updating the virtual environment

Follow the CMake workflow or the direct dependency commands in the developer guide to update the root .venv and check the result.

YAML format

Top-level can be either a list of tasks or a mapping with a tasks key. The mapping form can also include plan-level metadata such as portfolio, project, managers, pocs, summary, fiscal_range_begin, fiscal_range_end, and execution.

portfolio: Advanced Simulation and Computing
project: Task-Parallel Project
managers:
  - Alice Example
pocs:
  - Casey Example, PI
summary: >
  High-level planning context for the task collection.
fiscal_range_begin: 27
fiscal_range_end: 29
execution:
  overview: >
    Overall execution context for the plan.
  sections:
    - id: deliverable_a
      label: Deliverable A
      description: >
        Narrative execution detail for this deliverable.

tasks:
  - id: DraftArchitecture
    label: Draft architecture
    bnr: DP1518130
    cost: $100K
    funding status: funded
    site: LANL
    type: labor
    tags:
      - architecture
    project: Planning System
    execution_section: deliverable_a
    description: Produce the first architecture draft.
    start: M1Q3FY26
    deadline: M2Q3FY26
    expected duration: 2
    milestone: Design
    priority: high
    status: complete
    dependencies: []
    risk:
      - type: scope
        level: medium
        description: Integration requirements may change during implementation.
        mitigation: Review the architecture with stakeholders before implementation starts.
    funding:
      fy27: 50K
      fy29: 100K

  - id: BuildParser
    label: Build parser
    project: Planning System
    description: Load task definitions from YAML and Python files.
    start: M2Q3FY26
    deadline: M2Q3FY26
    expected_duration: 1
    milestone: Implementation
    priority: high
    status: pending
    dependencies:
      - DraftArchitecture
    risk:
      - type: integration
        level: medium
        mitigation: Add schema validation tests for both YAML and Python task sources.

  - id: MultiYearDelivery
    label: Multi-year delivery
    site: LANL
    project: Planning System
    funding:
      fy27: 50K
      fy28: 100K
    parts:
      - id: A
        label: First phase
        description: Complete the first phase.
        start: M1Q1FY27
        deadline: M3Q2FY27
        expected duration: 6
        milestone: Phase A
        priority: high
        status: active
        dependencies: []
        risk:
          - type: schedule
            level: low
            mitigation: Review progress monthly.
      - id: B
        label: Second phase
        description: Complete the second phase.
        start: M1Q3FY27
        deadline: M3Q4FY28
        expected duration: 18
        milestone: Phase B
        priority: medium
        status: pending
        dependencies:
          - A
        risk:
          - type: technical
            level: medium
            mitigation: Keep integration tests current.

Python format

Define PLAN or plan in a .py file for metadata plus tasks. The legacy TASKS or tasks list still works.

PLAN = {
    "portfolio": "Advanced Simulation and Computing",
    "project": "Task-Parallel Project",
    "managers": ["Alice Example"],
    "pocs": ["Casey Example, PI"],
    "summary": "High-level planning context for the task collection.",
    "fiscal_range_begin": 27,
    "fiscal_range_end": 29,
    "execution": {
        "overview": "Overall execution context for the plan.",
        "sections": [
            {
                "id": "deliverable_a",
                "label": "Deliverable A",
                "description": "Narrative execution detail for this deliverable.",
            }
        ],
    },
    "tasks": [
        {
            "id": "DraftArchitecture",
            "label": "Draft architecture",
            "bnr": "DP1518130",
            "cost": "$100K",
            "funding_status": "funded",
            "site": "LANL",
            "type": "labor",
            "tags": ["architecture"],
            "project": "Planning System",
            "execution_section": "deliverable_a",
            "description": "Produce the first architecture draft.",
            "start": "M1Q3FY26",
            "deadline": "M2Q3FY26",
            "expected_duration": 2,
            "milestone": "Design",
            "priority": "high",
            "status": "complete",
            "dependencies": [],
            "risk": [
                {
                    "type": "scope",
                    "level": "medium",
                    "mitigation": "Review the architecture with stakeholders before implementation starts.",
                }
            ],
            "funding": {"fy27": "50K", "fy29": "100K"},
        }
    ],
}

Status values

Use one of:

  • pending
  • active
  • ongoing
  • blocked
  • unfunded
  • complete

Fiscal period values

start and deadline must use M{month}Q{quarter}FY{year}:

  • month is 1 to 3 within the quarter
  • quarter is 1 to 4
  • year is a 2-digit fiscal year, for example FY26

Fiscal years begin on October 1:

  • Q1 = October through December
  • Q2 = January through March
  • Q3 = April through June
  • Q4 = July through September

Examples:

  • M1Q1FY26 = October 2025
  • M2Q3FY26 = May 2026
  • M3Q4FY26 = September 2026

Commands

  • validate: checks required fields, invalid status values, invalid fiscal period or duration values, invalid ids, duplicate ids, missing dependencies, and dependency cycles
  • list: prints tasks in Word activity and task-number order with each task's description, numbered dependencies, and status. Linked activity headings also show their execution section descriptions. Activity and task descriptions wrap at 80 characters. A gray block line separates tasks within an activity. Darker gray double rules align with activity headings before each activity and between its description and first task. It uses color when stdout is a compatible terminal; --color always or --color never overrides automatic detection. NO_COLOR disables automatic color. Accepts a task file or uses TUXFAN_PLANNER_DATAFILE.
  • list-detail: prints the full task details in deadline order, including fiscal start and deadline values and expected duration in months.
  • summary: groups tasks by project and milestone and prints funding totals when task funding is present
  • schedule: prints tasks in dependency order and marks them as READY, BLOCKED, UNFUNDED, ACTIVE, ONGOING, or COMPLETE
  • export: writes a Word plan for a .docx output path or a graphical plan for .svg. Add --include-notes or set include_notes: true in export options to show an italic Notes: line after each task description. Use --export-options PATH or TUXFAN_PLANNER_EXPORT_OPTIONS to control optional task attributes in both formats. The Word document includes a schedule and a detailed task table, starting on a new page with its section headings. When fiscal years are configured, the table includes one column per year with each task's funding level or a blank cell, plus a final total row. The SVG uses the same activity letters and task numbers as Word, and shows fiscal-year funding totals, completion years, and numbered dependencies. Its fill color reflects status, border color reflects risk, and an accent bar reflects priority. Both formats keep multipart task parts adjacent. Custom column labels and alignment apply only to Word.
  • export-gantt: writes a fiscal-month Gantt chart as .svg or .pptx, selected by the output file extension. Bars span each task's stated start through deadline; expected_duration does not move their dates. By default, the axis covers the configured fiscal year range exactly; tasks outside it are omitted and overlapping bars are clipped. Without configured fiscal years, it covers task and completion dates. Optional inclusive --from and --through bounds override the corresponding axis endpoints and accept a fiscal year such as FY26 or an exact period such as M1Q1FY26; a fiscal year expands to its first or last month as appropriate. Rows follow execution activity order; each task row keeps its number and label on one line when they fit, otherwise wraps the label at a word boundary within the two-line cell. Arrows leave the dependency bar's right edge and enter the dependent bar's left edge, routing around overlaps without bending farther right than either bar requires; they connect bars within each activity, and PowerPoint draws an arrow when both bars appear on the same slide. Status colors and completion markers identify progress. The SVG is a vector image; the PowerPoint file uses editable native shapes and splits activities into slides of up to ten tasks, with additional slides for timelines longer than five fiscal years. Copy the desired slide into an existing presentation. Gantt exports do not use task table export options.

Export options

Export options files can be YAML, YML, or Python. The supported settings are task_table_attributes, task_table_columns, and include_notes. The first two control the optional task attribute columns included in the Word export summary table and the attributes shown on SVG task cards. Custom labels and alignment apply only to Word. The .docx table always starts with an unlabeled column containing generated task numbers; it does not include a Project column. An Activity A, Activity B, etc. row precedes each activity's tasks, which appear in numeric task order. When tasks link to execution sections, the activity row includes the section label and its letter follows section order (for example, Activity B: Specialization Work with Task B.1). Unlinked tasks follow in project-based groups; plans without links keep their existing project-based grouping. Each activity label occupies one left-aligned cell spanning the table. The column header repeats only when the table continues onto another page; Activity rows appear at their normal group transitions. All table cells center their content vertically. Fiscal-year columns are added automatically when plan fiscal years are configured, with a final Total Funding row that sums each year and counts inherited multipart funding once. For completed tasks, those columns become one green-filled cell labeled with the completion year (for example, Completed FY26) when a completed period is available, or Completed otherwise; the other cells remain black on white. The other task metadata columns and per-task attribute narrative are limited to the attributes listed here.

Set include_notes: true in an export options file, or pass --include-notes to export, to show italic notes, including the Notes: label, after task descriptions. Notes are hidden by default. Select notes as a table attribute when you also want a Notes column in the Word summary table.

In the Word risk mitigation section, the bold risk label is green for low, yellow for medium, orange for high, and deep red for extreme. Mitigation text remains black.

Top-level Word section labels, including Tasks:, are bold and underlined.

Supported attribute names:

  • bnr
  • cost
  • funding or funding_status
  • notes
  • site
  • type
  • tags

Simple YAML:

task_table_attributes:
  - site
  - bnr
  - funding
  - tags

Shorthand YAML with custom labels:

task_table_attributes:
  - bnr: BNR
  - funding: Status
  - tags: Keywords

Recommended explicit YAML when you need labels or alignment:

task_table_columns:
  - attribute: bnr
    label: BNR
  - attribute: funding
    label: Status
  - attribute: tags
    label: Keywords

Supported column alignment values:

  • left
  • center
  • right

alignment is optional and defaults to center.

Example CLI usage:

planner export planner/examples/tasks.yaml /tmp/plan.docx --export-options planner/examples/export-options.yaml

Metadata

Release files for tuxfan-planner 0.2.3

For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.

Source distribution (sdist)

Source distribution for tuxfan-planner 0.2.3
File Size Uploaded Provenance
tuxfan_planner-0.2.3.tar.gz 64.4 kB Without provenance Details

Built distribution (wheel)

Table of built distributions (wheels) for tuxfan-planner 0.2.3
File Interpreter ABI Platform
tuxfan_planner-0.2.3-py3-none-any.whl Python 3 none any Details

Total release size: 104.7 kB

Release files / tuxfan_planner-0.2.3.tar.gz

Download URL tuxfan_planner-0.2.3.tar.gz
Size 64.4 kB
Tags Source
SHA-256 checksum
How to use checksums
91c9ac004ecad925d4ee9293a0a92d00b6854c365f4e7372eca9183aa5333f5f
BLAKE2b-256 checksum
How to use checksums
c57918de8c37d2869380677d27afc2829fc4052fa3cab405d4b10a2ffe54da76
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
No
Uploaded via twine/7.0.0 CPython/3.14.8

Release files / tuxfan_planner-0.2.3-py3-none-any.whl

Download URL tuxfan_planner-0.2.3-py3-none-any.whl
Size 40.3 kB
Tags Python 3
SHA-256 checksum
How to use checksums
8974d1b47c1a1e18bb51d6071d13b1a445a4f79ea419ccab30d38d10e404bdd3
BLAKE2b-256 checksum
How to use checksums
40183bf4804e7164b05e751aba59c35367a8aaaab029c55c29af26fdb6a3aa3f
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
No
Uploaded via twine/7.0.0 CPython/3.14.8

Security for tuxfan-planner 0.2.3

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

No provenance found

None of the files in this release were uploaded with provenance metadata.

A note on package security

PyPI is a repository for distributing packages, not a service for auditing them. While third-party security researchers and our staff do their best to detect and remove malicious packages, PyPI cannot guarantee the quality, security or suitability of any given package.

Anthropic, PBC Visionary sponsor Bloomberg Visionary sponsor Hudson River Trading Visionary sponsor Meta Visionary sponsor NVIDIA Visionary sponsor Microsoft Sustainability sponsor Depot Continuous Integration AWS Cloud computing and Security Sponsor Datadog Monitoring Fastly CDN Google Download Analytics Sentry Error logging StatusPage Status page