trueppm-scheduler
Project-schedule math as a library — critical path and delivery-risk forecasting, without a 500 MB desktop app or a SaaS subscription.
Answer the two questions every plan has to answer:
- "What's the earliest this can finish, and which tasks can't slip?" — a full forward/backward critical-path pass computes early/late dates, total and free float, and flags the tasks on the critical path.
- "How confident are we in that date?" — Monte Carlo simulation turns three-point estimates into a P50/P80/P95 forecast, so you can commit to a date you'll actually hit instead of the best-case one.
It's pure Python with just networkx and numpy underneath — no Django, no web server, no GUI. Drop it into a backend, a data pipeline, a Jupyter notebook, or a CLI and get the same engine that powers the TruePPM platform.
Why reach for this
- Real scheduling semantics, not a toy. All four dependency types (finish-to-start, start-to-start, finish-to-finish, start-to-finish) with lead/lag on every link — most lightweight schedulers only do finish-to-start, which cannot express an overlap or a wait without faking it with a dummy task.
- Working-time aware. A built-in working-day calendar skips weekends and honors holiday exceptions, so durations resolve to real delivery dates.
- Risk forecasting built in. PERT-Beta Monte Carlo (a Beta moment-fitted to the classic PERT mean and σ = (P − O)/6 — see Conventions), numpy-vectorized at ~10k runs/sec — the difference between "due March 3" and "70% likely by March 3, 95% by March 14."
- Fails loud on bad input. Cycle detection that names the offending task IDs, plus up-front validation of durations, lag, and project span — no silent wrong answers, no spinning on a degenerate graph.
- Embeds anywhere. Two dependencies, no framework. Serialize a plan to JSON, schedule it, and read back structured results.
Features
- Forward/backward CPM pass with all four dependency types (FS, SS, FF, SF), total/free float, and critical-path flagging
- Calendar-aware working-day arithmetic (weekend skip + holiday exceptions), with optional per-task calendars for mixed-team schedules
- Monte Carlo schedule-risk simulation via PERT-Beta distributions — method-of-moments fit to the classic PERT mean and σ = (P − O)/6, not the λ=4 Beta-PERT (numpy-vectorized, ~10k runs/sec) → P50/P80/P95 completion dates
- Hybrid agile/waterfall forecasting — mark a task
delivery_mode=SCRUMwith astory_pointsestimate and Monte Carlo samples its duration from the team's own velocity history instead of a per-task PERT guess, so a project can mix sprint-delivered and traditionally-estimated work in one simulation - Explainable results —
derive_value()answers "why is this date what it is?" for any early/late/float value, naming the exact predecessor, dependency type, and lag that won, plus every constraint it beat - JSON round-tripping for plans (
Project.from_json()/Project.to_json()) - CLI:
trueppm-scheduler schedule/trueppm-scheduler monte-carlo
Install
pip install trueppm-scheduler
Requires Python 3.11+.
Quick start
from datetime import date, timedelta
from trueppm_scheduler import schedule, Calendar, Project, Task, Dependency, DependencyType
calendar = Calendar() # Mon–Fri, no holidays (whole-day scheduling)
task_a = Task(id="t-1", name="Design", duration=timedelta(days=5))
task_b = Task(id="t-2", name="Build", duration=timedelta(days=10))
dep = Dependency(predecessor_id="t-1", successor_id="t-2", dep_type=DependencyType.FS)
project = Project(
id="p-1",
name="My Project",
start_date=date(2026, 1, 5),
tasks=[task_a, task_b],
dependencies=[dep],
calendar=calendar,
)
result = schedule(project)
build = next(t for t in result.tasks if t.id == "t-2")
print(build.early_finish) # 2026-01-23 (15 working days from 2026-01-05, across two weekends)
Scheduling granularity. The engine schedules in whole working-day units.
Calendar.hours_per_dayandCalendar.timezoneround-trip through serialization for API parity but are not consumed by the CPM or Monte Carlo passes — they do not change any computed date. Sub-day scheduling is a future change.
Duration and lag are counted in different units
This trips people up, so it is worth stating plainly:
| Input | Unit |
|---|---|
Task.duration (and every PERT estimate) |
Working days — weekends and calendar exceptions are skipped |
Dependency.lag |
Calendar days — the offset is applied as elapsed time, and only the resulting date is then snapped forward to the next working day |
So a 5-working-day task starting Monday finishes Friday, not the following Tuesday. But a 2-day FS lag after a Friday finish does not buy two working days of wait — the weekend absorbs it:
# Predecessor finishes Friday 2026-01-09, Mon–Fri calendar, FS link.
#
# lag=0d → successor starts Mon 2026-01-12 (1 working day later)
# lag=1d → successor starts Mon 2026-01-12 (1 working day later)
# lag=2d → successor starts Mon 2026-01-12 (1 working day later)
# lag=3d → successor starts Tue 2026-01-13 (2 working days later)
# lag=4d → successor starts Wed 2026-01-14 (3 working days later)
If you need a wait of n working days, size the lag against the calendar the successor will actually land on — or model the wait as a zero-resource task, which is duration-counted and therefore calendar-aware end to end.
Negative lag (lead) is supported and follows the same calendar-day rule: the candidate date snaps forward to the next working day too, never backward. A lead that pulls the candidate into a weekend does not borrow the Friday before it — it lands on the Monday after:
# Predecessor A is 6 working days starting Mon 2026-01-05, so it finishes
# Mon 2026-01-12. FS link, lag=-3 (a 3-day lead).
#
# candidate = A.finish + 1 day - 3 days = Sat 2026-01-10
# Sat is non-working, so it snaps forward -> successor starts Mon 2026-01-12
#
# Not Fri 2026-01-09 — the engine never snaps a lead or lag backward.
Per-task calendars
By default every task is scheduled on the single Project.calendar. A task can
instead opt into its own working week — useful when one schedule spans teams or
projects that keep different calendars:
seven_day = Calendar(working_days=0b111_1111) # every day is a working day
support = Task(id="t-3", name="Hotfix", duration=timedelta(days=3), calendar_id="ops")
project = Project(
id="p-1",
name="My Project",
start_date=date(2026, 1, 5),
tasks=[task_a, support],
calendar=Calendar(), # pass-level default (Mon–Fri)
calendars={"ops": seven_day}, # registry tasks opt into by id
)
Conventions:
- Duration arithmetic uses the task's own calendar (
calendar_id→ entry inProject.calendars). Acalendar_idofNoneuses the pass-levelProject.calendar. WhenProject.calendarsis non-empty, acalendar_idwith no matching entry raisesInvalidScheduleInput— a typo is refused, not scheduled on the wrong working week. With no registry (Noneor empty) a setcalendar_idis ignored and the task usesProject.calendar. - Lag on a dependency edge is applied as calendar days (above) and then snapped on the successor's calendar: the constraint lands where the wait is actually consumed.
- It is fully backward compatible — a project with no
calendarsregistry schedules byte-for-byte as before. - Both passes honor them: the CPM
schedule()pass (early/late dates, float, criticality) andmonte_carlo(). A fully deterministic mixed-calendar project simulates to precisely its CPM finish date, so the two agree by construction.
See the full documentation for CPM output fields, Monte Carlo usage, and CLI reference.
Explaining a result
The CPM pass picks the max (forward) or min (backward) of several candidate
constraints for each date, then moves on — it doesn't remember which one won.
derive_value() replays that decision for a single task and value, and names
the constraint that actually set it:
from trueppm_scheduler import derive_value, Quantity
d = derive_value(project, task_id="t-2", quantity=Quantity.EARLY_START)
print(d.value, d.binding.kind, d.binding.source_task_name, d.binding.dep_type)
# 2026-01-12 predecessor_fs Design FS — Build starts when Design finishes on an FS link
for c in d.contributions:
print(c.kind, c.source_task_name, c.is_binding) # every constraint considered, winner flagged
This is what lets a UI (or an AI agent) answer "why is this task starting on the 17th?" with the actual dependency instead of a guess — the value returned is computed the same way the engine computed it, not re-derived heuristically.
Mixing agile and waterfall in one schedule
Real programs are rarely pure CPM or pure Scrum. A task can opt into sprint-based uncertainty instead of a three-point estimate:
from trueppm_scheduler import DeliveryMode, Task
sprint_work = Task(
id="t-4",
name="Checkout redesign",
duration=timedelta(days=10), # fallback if delivery_mode is later cleared
delivery_mode=DeliveryMode.SCRUM,
story_points=21,
)
project = Project(
...,
tasks=[task_a, task_b, sprint_work],
velocity_samples=[18, 22, 15, 24, 19], # the team's last five sprints
)
monte_carlo() then samples sprint_work's duration from how many sprints the
team's own velocity history says 21 points takes — not from a PERT guess nobody
on the team would stand behind — while every other task in the same run still
uses its three-point estimate. DeliveryMode.WATERFALL (the default) is
unaffected; mixing modes is opt-in per task.
Interpreting the output
The two entry points answer different questions, and their outputs are not the
same kind of thing. Reading a schedule() date as if it were a commitment is
the single most common way to misuse this library.
schedule() returns one date, and it is the optimistic one. The CPM finish
is the earliest feasible completion — the date you get if every task takes
exactly the duration you estimated, no task slips, and no risk fires. It is a
point on a distribution, not the distribution. Nothing about the forward pass
makes that point likely; it is simply the arithmetic consequence of the numbers
you fed it.
monte_carlo() returns the distribution that date sits in. Sampling each
task's duration and re-running the network thousands of times produces the
range of finishes the plan can actually deliver:
| Percentile | Reading | Use it for |
|---|---|---|
p50 |
Half the simulated runs finished on or before this date. In practice it lands close to the CPM finish. | A midpoint, never a commitment |
p80 |
4 in 5 runs finished by this date. | The commitment date — internal and stakeholder plans |
p95 |
19 in 20 runs finished by this date. | Contractual deadlines, launch dates, regulatory submissions |
So a CPM finish of 2026-03-03 and a P80 of 2026-03-14 do not disagree. They
say: the plan can finish on March 3, and it will finish by March 14 four times
out of five. Committing to March 3 is committing to a coin flip.
Two consequences worth internalizing:
- A task with no three-point estimate contributes no uncertainty. It uses
its fixed
durationon every run, so a project where nothing is estimated simulates to precisely the CPM finish —p50 == p80 == p95. That is a correct result, not a broken one: you asked what varies, and the answer was nothing. Add optimistic/most-likely/pessimistic values to the tasks that drive the date (MonteCarloResult.sensitivityranks them) to get a real band. - Widening the band is not pessimism. A pessimistic estimate set to
most_likely × 1.2produces a distribution too narrow to be useful — PERT derives σ as(P − O) / 6, so a P barely above M encodes near-certainty. The P value should describe a realistic bad day.
The same framing, with the underlying math, is in the Monte Carlo documentation.
Scope. Only this package's Python engine runs Monte Carlo. The companion Rust/WASM engine (
trueppm-wasm-scheduler, used for browser-side and offline recompute) implements the deterministic CPM pass only — there is no probabilistic path there to keep in conformance.Both engines are tested against each other and, separately, against an independent reference CPM written from the conventions below. The fields that comparison covers exactly, and the ones it does not, are listed in CONTRIBUTING.md.
Conventions
Every modeling rule the engine commits to, one line each, with the issue or ADR that decided it. Differs marks the rules where a schedule built in MS Project or Primavera P6 can come out differently here; everything else follows their convention. The same list, with the comparison spelled out, is on Scheduler Conventions.
Units and calendars
- Durations and three-point estimates count working days, in whole days only; a sub-day duration or lag raises
InvalidScheduleInput. Differs — both tools schedule in hours. (#826) Calendar.hours_per_dayandCalendar.timezoneare inert — they round-trip and change no date. Differs. (#4131)- Lag counts calendar days; the resulting date always snaps forward to the successor's next working day — a lead (negative lag) follows the same rule and never snaps backward. Differs — MS Project and P6 count lag in working time by default. (#2534; open question #2535)
- Per-task calendars: duration expands on the task's own calendar, lag is consumed on the successor's. (ADR-0120)
Links and constraints
- An FF/SF-driven task stays contiguous and right-aligned on its pinned finish, so its start moves back — the MS Project convention. Consequence: CPM is non-monotone in duration on an FF/SF network (a longer task can start earlier). (#3806, decided: keep)
- A zero-lag FF and a zero-lag SS on a whole-day Standard calendar reproduce the Start/Finish MS Project itself computed and saved for the same tasks — confirmed against a real MS Project export (
LinkTypes.mpp), not just the documented rule. (#4323) - An SF link finishes the successor at the start of the predecessor's start day — with zero lag, its last working day is the day before. A positive lag counts from the predecessor's start itself, so a weekend just before it cannot absorb the lag (a Monday start with
SF+2dfinishes the successor Tuesday); a lead counts back from the zero-lag finish. Verified for the zero-lag, ordinary-work case against a real MS-Project-saved schedule (tests/fixtures/msproject/link_types_2013.py, whose SF predecessor starts on a Tuesday), and now for a positive lag against four independently-corroborated MS-Project-saved alignments (tests/fixtures/msproject/task_links_cross_version.py, #4327) — including the Monday-start, weekend-adjacent-anchor case #4333 reports: all four agree with MS Project, confirming the #4333 fix against external file evidence rather than only the hand-built regression test intests/test_sf_from_work.py. A second, separate divergence remains (#2534): the engine counts lag in calendar days and snaps forward once, so a lag long enough to reach a second weekend from the anchor again finishes one working day short of MS Project — confirmed on all four alignments by raising their lag past what the saved files actually used (e.g. the Monday-start case agrees through lag=6 and diverges again at lag=7; a mid-week start diverges as early as lag=3). An SF link out of a milestone remains unverified — no MS Project sample found covers it (#4327). (#4145, #4322, #4333, #2534) - A task with an SF link may be placed before the project start: its project-start floor is the earlier of the project start and its SF placement, which its SF links already enforce, so the project start never holds it back, and a binding FS, SS or FF lead can also place it there. A task with no SF link keeps the floor, so its leads stay floored. A data date or
planned_startafter the project start, and a recordedactual_start, hold every task. A shorter lag never finishes work later; on a network of tasks with work, an FS, SS or FF link that does not bind moves nothing. MS Project's behavior for mixed links and for leads is unverified (#4319). (#4218, #4220) - A data date at or before the project start moves nothing, and neither does such a
planned_start(SNET) on a task with no SF link. Snapped to the task's calendar, a bound on or before the project's first working day is the project-start floor, so the engine treats it as that floor: every task that takes the project start already has it, and the places that leave it out (an SF-linked task, and the instant a milestone's successors measure their lags from, both below) do not get it back through it. So addingstatus_date <= start_datechanges no task's dates, floats or the finish, anullstatus date schedules exactly like one on the start, and an SNET on or before the start changes nothing on a task with no SF link. This matters because callers often default the data date to today: on a project that starts in the future that is a date before the start, and it used to pull a free milestone's successors up to (start − today) days earlier. The data-date half applies to SF-linked tasks too, which is a decision, not a consequence: a sub-start data date could hold an SF-linked task that its link places even earlier, and it no longer does. An SNET on an SF-linked task is kept verbatim, even before the start: such a task takes no project-start floor, so the SNET can only hold it later than its links place it, and snapping a task to the project start (or moving the start to it) writes exactly that SNET. A recordedactual_startis kept verbatim, because a fact may precede the plan. A data date or SNET after the start binds as before. (#4635) - A zero-duration milestone is an instant: at the end of its driver's finish day, or the start of the day a floor holds it to. A lag, or a predecessor's recorded finish on a non-working day, that places it after a weekend or holiday shows it at the start of the next working day — confirmed for the work-driven case against a real MS Project export with all 10 zero-duration milestones in a saved
.mppchain. The project start only bounds the day a milestone is shown on: a milestone that a lead or an SF-placed predecessor puts before it is shown on the project's first working day (unless it has an SF link of its own), but its successors' lags count from the earlier point — unverified against MS Project or P6 (#4225). Its start and finish are one instant, so an FF link into a milestone places it exactly where FS does, a lagged SF link places it on its anchor plus the lag (a positive lag counts from the predecessor's start itself), and an FF link out of it measures a positive lag from that instant; with no lag or a lead it counts from the end of the working day before the milestone, so a longer lead never finishes the successor later. (#4079, #4173, #4225, #4272, #4273, #4323) - The only date constraint is start-no-earlier-than, via
planned_start;planned_finishis reserved and inert — no deadline, finish, must-start-on or ALAP constraint. Differs. (#3345, #804) - An SS or SF link from a summary task is rejected (FS/FF from a summary expand to its leaves). Differs — MS Project accepts it. (ADR-0370)
Progress and actuals
- A completed task (
actual_finishset, or 100%) is pinned to its recorded dates verbatim — even on a non-working day — and is never re-sampled. With no recorded actuals it is pinned at the project start (or itsplanned_start, when later); no predecessor moves it. A completed milestone stays an instant: with no actuals at the start of its pinned day; with actuals on its recordedactual_finish(elseactual_start) day, at the edge of that day it had live — the end when completed work finishing that day placed it, or — while a predecessor is still open — whenTask.live_day_end_on(the day your previous run showed it at the end of) names that day; otherwise the start. No change to open work moves it, and when you pass your previous run's output back, closing it on its forecast day moves no successor (#4433, #4525). (ADR-0136) - An in-progress task schedules its remaining
duration − floor(duration × pct / 100)working days forward from the data date (status_date), floored at its unsnappedactual_start. (ADR-0132)
Float and output
is_criticalis exactlytotal_float == 0; total float is the working days from early to late start.free_floatinverts the forward constraint across all four link types, capped at total float; no live successor → total float. (#1828)- The order of
ScheduleResult.tasksis unspecified — look tasks up byid. (#1862) project_finishand a milestone'searly_finishare the day the finish is shown on, andmilestone_at_day_endsays which edge of it. The end of a Friday and the start of the next Monday are the same point in working time, so the shown day can hop a weekend or holiday with no working-time move. Compute slip in working time, reading a start-of-day milestone finish as the end of the working day before it — never as a calendar-day difference of two finishes. (#4178)- The same holds for Monte Carlo:
MonteCarloResult.p50/p80/p95are shown days, andp50_at_day_start/p80_at_day_start/p95_at_day_startsay which edge of each. Compare a percentile with the CPM finish, or with another run's percentile, in working time. (#4204) These are read-only properties overMonteCarloResult.percentiles, adict[int, Percentile]of the levels that were computed (Percentile(date, at_day_start)), soresult.percentiles[80].dateequalsresult.p80. (#4514)
Monte Carlo
- Three-point estimates sample a Beta fitted by method of moments to the classic PERT mean
(O + 4M + P) / 6and σ =(P − O) / 6— not the λ=4 Beta-PERT. Same mean; on a symmetric estimate the band is ~12% narrower (P80/P95 slightly earlier), on one whose mode sits at an end it is wider. Differs from @RISK's default. (ADR-1245, #4133) - Every sampled duration is floored at
Task.duration— the optimistic tail below the plan is not expressed. Differs — risk tools sample the whole estimate. (#3765) - "Never before the CPM finish" holds only on FS/SS-only networks; on an FF/SF network a percentile can land earlier, because CPM itself is non-monotone there. (#3806)
- A fixed
seedreproduces P50/P80/P95 on the same numpy andtrueppm-schedulerversions — see Reproducibility. (#4099)
Errors and input limits
Every exception the engine documents raising subclasses ValueError (via the
common SchedulerError base), so one except ValueError catches them all — but
each is individually catchable:
| Exception | Raised when |
|---|---|
CyclicDependencyError |
The dependency graph contains a cycle. .cycle lists the task IDs forming it. |
SimulationCapExceeded |
monte_carlo(runs=…) exceeds max_runs, or the project has more tasks than max_tasks. |
InvalidScheduleInput |
The input is structurally valid but out of range, or the wrong type (see below). |
UnknownTaskError |
derive_value(project, task_id, …) is called with a task_id that names no task in the project. |
What this guarantee actually covers. Project.from_dict() / Project.from_json()
— the untrusted-input path — type-check and coerce every field, so a malformed
document of any shape raises InvalidScheduleInput and never a bare
AttributeError/TypeError. Constructing Project/Task/Dependency directly in
Python (the direct-object API, as in every example above) is held to the same
field rules from_dict() applies, on every field of Project, Task,
Dependency and Calendar — including the fields the engine never reads: the
reserved Calendar.hours_per_day (a finite number) and timezone (a string), the
computed task dates (early_start … scheduled_start, plain date or None)
and floats (total_float/free_float, timedelta), the is_critical and
milestone_at_day_end flags (bool), and delivery_mode (a DeliveryMode or
None, not the string "scrum"). Calendar.working_days must be an integer in
[0, 127], and a calendars registry must be keyed by string ids. A wrong-typed
or out-of-range value (None, a string, a datetime, a bare int where a list or
timedelta is expected, an unhashable value, …) makes schedule() and
monte_carlo() raise InvalidScheduleInput, not a bare Python exception.
(derive_value() applies the same check when it schedules the project itself,
i.e. when called without result=.)
So any project schedule() accepts round-trips: Project.from_json(p.to_json())
loads it back unchanged and schedules it identically. to_dict() and to_json()
on Project (and to_dict() on Task, Dependency and Calendar) apply the
same rules and raise InvalidScheduleInput for a field they cannot serialize.
Construction itself stays lenient — the check runs when a project is scheduled or
serialized, so an object can be built partially and filled in first.
tests/test_exception_contract.py pins the per-field guarantee with a
single-field-mutation sweep over the init fields × 12 adversarial values × both
schedule()/monte_carlo() entry points (Task.id is excluded from that sweep;
a non-string task id is covered by the explicit examples in
tests/test_contract_fuzz.py), and tests/test_roundtrip_contract.py
property-tests the round trip, so a future field addition that reopens a gap fails
a test rather than becoming a silent leak.
The engine walks the working calendar one day at a time, so it also validates input up front rather than spinning on a degenerate project:
- Calendar —
working_daysmust be an integer bitmask in[0, 127]that sets at least one weekday bit (Mon–Sun); a calendar whoseexceptionsblanket the entire search window is rejected too. - Duration — each task duration must be between
0andMAX_DURATION_DAYS(36_525, ~100 years). Negative durations are rejected. - Lag — each dependency lag must be within
±MAX_LAG_DAYS(36_525). - Project span — the cumulative span (every task's worst-case duration plus
the magnitude of every lag) must stay under
MAX_PROJECT_SPAN_DAYS(366_000, ~1000 years), regardless of task count. - Monte Carlo —
runsmust be>= 1.
Project.from_json() also rejects the non-standard JSON literals NaN,
Infinity, and -Infinity.
from trueppm_scheduler import schedule, InvalidScheduleInput
try:
result = schedule(project)
except InvalidScheduleInput as e:
print("Bad input:", e) # "Task 't-1' duration exceeds the maximum of 36525 days (got …)."
Limits for embedders
The validator caps above are all exported from the top-level trueppm_scheduler
package, under the same names the error messages use, so an embedding
application can check or re-enforce them without hand-copying a number:
| Cap | Value | Bounds |
|---|---|---|
MAX_DURATION_DAYS |
36525 |
A single task's duration or PERT estimate (~100 years) |
MAX_LAG_DAYS |
36525 |
A single dependency's lag, either direction |
MAX_PROJECT_SPAN_DAYS |
366000 |
Cumulative project span — every task's worst-case duration plus every lag (~1000 years) |
MAX_DEPENDENCIES |
100000 |
Raw dependency-edge count, before summary expansion |
MAX_EXPANDED_EDGES |
100000 |
Leaf-level edges after expanding a summary↔summary dependency |
MAX_CALENDAR_EXCEPTIONS |
100000 |
Exception ranges on one Calendar |
MAX_CALENDAR_SCAN_DAYS |
36600 |
Longest run of consecutive non-working days before a calendar is declared degenerate |
MAX_LAG_DELTA_CELLS |
50000000 |
Monte Carlo's (distinct dep-type/lag combos) x (index span) precompute |
MAX_VELOCITY_SPRINTS |
10000 |
Per-run sprint horizon the velocity sampler will bootstrap |
MC_SENSITIVITY_CAP |
20 |
Tasks returned by the sensitivity ("tornado") ranking |
from trueppm_scheduler import MAX_DEPENDENCIES, MAX_DURATION_DAYS, MAX_LAG_DAYS
There is no fixed task-count or run-count cap built into the engine itself —
monte_carlo(max_runs=…, max_tasks=…) are opt-in, caller-supplied ceilings that
default to None (uncapped). That default is correct for a batch script or
notebook that owns the whole machine, and wrong for a synchronous web request:
schedule() and monte_carlo() are CPU-bound (a day-by-day calendar walk,
plus a numpy-vectorized sampling pass), so a request handler that calls either
directly on untrusted or unbounded input ties up a worker thread or process for
as long as the input demands. Pass max_runs and max_tasks whenever the
caller is untrusted, and run the call off the request thread with a wall-clock
timeout — a worker/queue, not inline in the view — the same pattern the
TruePPM API itself uses
(#4010).
A long calendar exception does not cost more as the dependency graph grows:
calendar-day lookups are index-backed (a cached, bisected merged-interval
index), so both the CPM pass and Monte Carlo snap to the next or previous
working day in O(log E) regardless of how many tasks or dependencies
reference that calendar.
API stability and versioning
The public API is the __all__ surface of the top-level trueppm_scheduler
package — the names you can import directly from trueppm_scheduler
(schedule, monte_carlo, Project, Task, Dependency, DependencyType,
Calendar, ScheduleResult, MonteCarloResult, the exception types, etc.).
Everything else — the trueppm_scheduler.engine internals, any underscore-
prefixed helper, and module layout — is unstable and may move or change
without notice.
This package is Development Status :: 4 - Beta as of 0.4.0b1: the public
API may still change before 1.0. Pin an exact version rather than a range:
trueppm-scheduler==0.4.0
Beta releases are pre-releases: pip installs a pre-release only when you pass
--pre, or when no final release satisfies the requirement yet. PyPI
currently holds only pre-releases of trueppm-scheduler (no version has
reached final), so today a bare pip install trueppm-scheduler falls into the
second case and installs the latest beta. Once 0.4.0 final ships, that
changes: a bare install will resolve to 0.4.0 and skip any later 0.5.0
betas unless you pass --pre — which is why pinning an exact version (above)
is the reliable approach in either state. Breaking changes are recorded in
CHANGELOG.md,
which also ships inside the wheel.
Heads-up: trueppm_scheduler.engine becomes a subpackage in 0.5
0.5 will split the single trueppm_scheduler/engine.py module into an
engine/ subpackage (CPM, Monte Carlo, calendar math, validation, and so on in
separate files). The split is planned to land on main in November–December
2026 and ship with 0.5
(#4550). It is a pure move:
scheduling results will not change.
Will keep working, unchanged:
- Every import from the top-level
trueppm_schedulerpackage (the__all__surface above). from trueppm_scheduler.engine import Xfor every name importable today, including underscore-prefixed helpers.engine/__init__.pyre-exports them for the whole 0.5 line.- Result objects pickled by 0.4 will still unpickle on 0.5.
Will need a change on your side:
- Patching engine internals in your tests.
unittest.mock.patch("trueppm_scheduler.engine._helper")ormonkeypatch.setattr(engine, "MAX_DEPENDENCIES", 1)will replace the re-exported name. The code that actually calls the helper or reads the constant will still see the original, so the patch stops taking effect, usually without failing the test. Point such patches at the submodule that defines the name once you upgrade. - Code that reads a class's
__module__, or tooling keyed on the file pathtrueppm_scheduler/engine.py(coverage or lint excludes, for example). - Result objects pickled by 0.5 will not unpickle on 0.4.
If you depend only on the public API, there is nothing to do.
Reproducibility (seeded runs)
Monte Carlo simulation is reproducible for a fixed seed: the same seed
always yields the same P50/P80/P95 forecast for the same input, on the same
numpy version and the same trueppm-scheduler version. Within that envelope
this is a supported, tested property you can rely on for reproducible reports
and regression baselines — not an implementation detail.
Outside it, it is not promised. The dependency range is numpy>=1.26,<3, and
numpy guarantees a Generator's random stream (Generator.beta included) only
within one release (NEP 19),
so upgrading numpy can move seeded percentiles. A trueppm-scheduler release
can move them too — a sampling fix or a change to the order tasks are sampled
in is recorded in the changelog. If a seeded baseline must stay bit-identical,
pin both packages alongside the seed.
This is a statement about repeatability of the sampling, not about the shape
of the answer — a seeded Monte Carlo run still returns a probability
distribution. Do not confuse it with the deterministic single-date output of
schedule(), which is a different thing entirely.
Status and roadmap
0.4 — the current release. The CPM pass (all four dependency types,
calendar-aware lag, cycle detection) and Monte Carlo simulation (PERT-Beta,
velocity sampling, derive_value() explainability) are stable and exercised
by the fuzz, mutation, and MS-Project-parity suites described in
CONTRIBUTING.md.
Known limitations open against 0.4, grouped by area — every item below is an open issue; nothing in this list is fixed yet, regardless of which future release it is scheduled for:
- CPM correctness — while any predecessor of a closed milestone is still
open, its frozen day edge (
live_day_end_on) reflects the last derivation, so correcting a completed predecessor's actuals or removing a link is not re-read until every predecessor completes (#4574); a work-task late-finish seed can ignore a start-of-day project finish on wider calendars (#4436); FF/SF links into a summary task do not fan out to every leaf the way the successor side does (#4437);perturb_task_duration(duration=0)on a started milestone can mark it complete and move the schedule as a side effect of the perturbation (#4536);driving_edgescan omit a link whose calendar-day lag lands on non-working time even though removing it does move the successor (#4537);expand_summary_dependenciescan invent a sibling ordering from a summary-to-own-child link thatfind_cyclecorrectly flags as a cycle (#4538); a completed task with no recorded actuals can be moved later than the data date, a non-monotonicity where knowing less about a task slips the schedule further than knowing more (#4539); and several MS-Project-parity cases — SF out of a milestone, mixed SF+FS/SS/FF at the project-start floor — remain unverified against a real MS Project export (#4327, #4319). - Monte Carlo — a velocity-sampled duration is re-expanded
against the task's own calendar rather than the sprint calendar it was
sampled against
(#4529); sprint-horizon
clamping truncates the slow tail of a velocity-driven P80/P95, so it reads
as a lower bound rather than a full forecast
(#2469); three
monte_carlo()keyword caps still leak a bareTypeErrorinstead of the documentedSchedulerErrorcontract (#4464); and percentile estimation is imprecise at very low run counts (10–11 runs), where the reported P95 can have only 90% of runs on or before it (#4540). - Calendars — a zero-lag milestone-to-milestone link into a narrower per-task calendar can overstate float (#4526).
- Scale / performance — a project above roughly 73,000 tasks at a 5-day
average duration is refused as "longer than 1,000 years" by a span guard
meant to catch pathological input, not real large projects
(#3830); Monte Carlo
holds three
(runs × tasks)float64 matrices live in memory, already 2.3 GB at 50,000 tasks (#3824). - API contract / errors — the derivation vocabulary
(
DerivationContribution.kind,Derivation.quantity/pass_) is still an open string, not a published enum (#4291), and exported dataclasses document their fields in source comments rather than Google-styleAttributes:sections, so they do not render in a generated API reference (#4471). - WASM engine —
wasm-schedulererrors are untyped strings at 17 call sites rather than a structured error type (#4474), and the CPM invariant-property suite that fuzzes the Python engine has no Rust port yet, so a Rust-only regression would not be caught the same way (#4270).
Committed for 0.5. 0.5 will run a hardening pass over the engine
(#3988) rather than ship
new scheduling features; the following are release::committed for 0.5 —
they will ship with 0.5 or that release will slip:
- Engine decomposition and correctness hardening — splitting
engine.pyinto a subpackage without breaking imports (see the heads-up above; #4550) and extending the independent CPM oracle to milestone late dates/floats (#4275); mutation-testing phase 2 bringsengine.pyitself into scope (#2468); three more bare-exception leaks close theSchedulerErrorcontract (#4162, #4132); and the span-guard bug above will be fixed, raising the supported envelope toward 50,000 tasks (#3830, #3825). - Performance — a published
pytest-benchmarksuite at 100–5,000 tasks, with measured numbers in this README (#4230); the Monte Carlo memory footprint above is chunked over runs and dropped to float32 (#3824); the CPM duration-expansion day-walk above moves off O(duration) (#1531). - Monte Carlo correctness — the sprint-horizon clamp bug above will be fixed (#2469); an in-progress task's sampled duration no longer has its optimistic tail truncated by subtracting deterministic elapsed time from the sampled total (#1495).
- Scheduling semantics — the calendar-day-vs-working-day lag question will be decided (#2535); deadline-driven negative float will surface "behind committed date" in CPM output (#804); and partial resource allocation (e.g. someone at 60%) will be enforced in the CPM/leveling pass (#84, #744).
- Packaging — stale/placeholder
CITATION.cffmetadata (a fake ORCID and DOI) will be corrected (#3857).
May also land in 0.5, but not committed: the velocity-sampled duration
re-expansion on the wrong calendar above
(#4529), the
FF/SF-into-summary fan-out and derive_value() binding/imposed_date
mismatch above
(#4437,
#4438), the remaining
MS-Project-parity gaps, the zero-lag milestone-calendar overstatement
(#4526), the three leaking
Monte Carlo keyword caps, a monte_carlo(return_samples=True) option to
hand back the raw matrices
(#4166), and five findings
from the 2026-10-18 scheduler audit above: the perturb_task_duration
milestone side effect
(#4536), the
driving_edges false negative on calendar-lag-onto-non-working-time
(#4537), the
expand_summary_dependencies sibling-ordering bug on invalid input
(#4538), the
completed-task-without-actuals non-monotonicity
(#4539), and Monte Carlo
percentile imprecision at very low run counts
(#4540).
Later — a sequence, not a schedule. Versions past 0.5 carry no date; what ships and in what order is set by evidence from the 0.4 beta and 0.5, not by this list (full rationale on the roadmap). 0.6 will open the write surface safely — an engine-as-referee that will refuse any agent write which would create an impossible schedule, building on the 0.5 plan-mode dry run — and will start the hybrid human/AI engine depth begun in 0.5: sub-day scheduling, an explicit effort-vs-duration split, and a probabilistic human-fallback branch for agent-delivered work. 0.6 is also planned to bring the OSS resource-leveling pass: CPM assumes infinite resources today, and leveling will resolve the conflicts the 0.5 pre-commit warning only flags. 0.7 is planned to bring resource-constrained Monte Carlo once the sampler's own correctness checks are in place, Rust/WASM leveling parity, and probabilistic branching (conditional paths sampled per run). 0.8 is planned to add task splitting (interruptible, resumable duration).
Security
Found a vulnerability in the scheduling engine? Please report it privately —
do not open a public issue. Email security@trueppm.com or open a
confidential GitLab issue. Full policy, response SLAs, and safe-harbor terms are
in SECURITY.md
at the monorepo root.
License
Apache 2.0
Metadata
Release files for trueppm-scheduler 0.4.0
For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.
Source distribution (sdist)
| File | Size | Uploaded | Provenance | Actions |
|---|---|---|---|---|
| trueppm_scheduler-0.4.0.tar.gz | 510.4 kB | With provenance | Details for trueppm_scheduler-0.4.0.tar.gz |
Built distribution (wheel)
| File | Interpreter | ABI | Platform | Actions Reset |
|---|---|---|---|---|
| trueppm_scheduler-0.4.0-py3-none-any.whl | Python 3 | none | any | Details for trueppm_scheduler-0.4.0-py3-none-any.whl |
Total release size: 709.2 kB
Release files / trueppm_scheduler-0.4.0.tar.gz
| Download URL | trueppm_scheduler-0.4.0.tar.gz |
|---|---|
| Size | 510.4 kB |
| Tags | Source |
|
SHA-256 checksum How to use checksums |
f252703599d4b2234f7749d2f7061f1f4b8753c48d2c054726d97ac3a470f056
|
|
BLAKE2b-256 checksum How to use checksums |
af9b0e6ada4746b8880b3d7393652b2c4a96a44becffb6d377de7c660d501ed6
|
| Upload date | |
|
Uploaded using Trusted Publishing? What is trusted publishing? |
Yes |
| Uploaded via |
twine/7.0.0 CPython/3.11.15
|
Provenance
Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.
PyPI Publish Attestation
PyPI verified that this artifact, at this checksum, originated from the publisher listed below.
Signed by GitLab CI/CD, verified by PyPI on Oct 31, 2026.
Transparency logRelease files / trueppm_scheduler-0.4.0-py3-none-any.whl
| Download URL | trueppm_scheduler-0.4.0-py3-none-any.whl |
|---|---|
| Size | 198.9 kB |
| Tags | Python 3 |
|
SHA-256 checksum How to use checksums |
8be45bce622b2e8fdff3ef391475025ebe5657bebef982b9645ae2774f57ca6e
|
|
BLAKE2b-256 checksum How to use checksums |
67ad9b8ebda62fd8ba033d669ca5ac52d391d3f6deb0479e1233df6f68c08f25
|
| Upload date | |
|
Uploaded using Trusted Publishing? What is trusted publishing? |
Yes |
| Uploaded via |
twine/7.0.0 CPython/3.11.15
|
Provenance
Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.
PyPI Publish Attestation
PyPI verified that this artifact, at this checksum, originated from the publisher listed below.
Signed by GitLab CI/CD, verified by PyPI on Oct 31, 2026.
Transparency logSecurity for trueppm-scheduler 0.4.0
Provenance
Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.
Full provenance
Both files in this release have been uploaded with provenance metadata.
Attestation for trueppm_scheduler-0.4.0.tar.gz
PyPI Publish Attestation
PyPI verified that this artifact, at this checksum, originated from the publisher listed below.
Signed by GitLab CI/CD, verified by PyPI on Oct 31, 2026.
Transparency logA note on package security
PyPI is a repository for distributing packages, not a service for auditing them. While third-party security researchers and our staff do their best to detect and remove malicious packages, PyPI cannot guarantee the quality, security or suitability of any given package.
To learn more about protecting yourself from malicious actors, visit our package security documentation.