trueppm-scheduler

PyPI version PyPI downloads CI License

Project-schedule math as a library — critical path and delivery-risk forecasting, without a 500 MB desktop app or a SaaS subscription.

Answer the two questions every plan has to answer:

  • "What's the earliest this can finish, and which tasks can't slip?" — a full forward/backward critical-path pass computes early/late dates, total and free float, and flags the tasks on the critical path.
  • "How confident are we in that date?" — Monte Carlo simulation turns three-point estimates into a P50/P80/P95 forecast, so you can commit to a date you'll actually hit instead of the best-case one.

It's pure Python with just networkx and numpy underneath — no Django, no web server, no GUI. Drop it into a backend, a data pipeline, a Jupyter notebook, or a CLI and get the same engine that powers the TruePPM platform.

Why reach for this

  • Real scheduling semantics, not a toy. All four dependency types (finish-to-start, start-to-start, finish-to-finish, start-to-finish) with lead/lag on every link — most lightweight schedulers only do finish-to-start, which cannot express an overlap or a wait without faking it with a dummy task.
  • Working-time aware. A built-in working-day calendar skips weekends and honors holiday exceptions, so durations resolve to real delivery dates.
  • Risk forecasting built in. PERT-Beta Monte Carlo (a Beta moment-fitted to the classic PERT mean and σ = (P − O)/6 — see Conventions), numpy-vectorized at ~10k runs/sec — the difference between "due March 3" and "70% likely by March 3, 95% by March 14."
  • Fails loud on bad input. Cycle detection that names the offending task IDs, plus up-front validation of durations, lag, and project span — no silent wrong answers, no spinning on a degenerate graph.
  • Embeds anywhere. Two dependencies, no framework. Serialize a plan to JSON, schedule it, and read back structured results.

Features

  • Forward/backward CPM pass with all four dependency types (FS, SS, FF, SF), total/free float, and critical-path flagging
  • Calendar-aware working-day arithmetic (weekend skip + holiday exceptions), with optional per-task calendars for mixed-team schedules
  • Monte Carlo schedule-risk simulation via PERT-Beta distributions — method-of-moments fit to the classic PERT mean and σ = (P − O)/6, not the λ=4 Beta-PERT (numpy-vectorized, ~10k runs/sec) → P50/P80/P95 completion dates
  • Hybrid agile/waterfall forecasting — mark a task delivery_mode=SCRUM with a story_points estimate and Monte Carlo samples its duration from the team's own velocity history instead of a per-task PERT guess, so a project can mix sprint-delivered and traditionally-estimated work in one simulation
  • Explainable results — derive_value() answers "why is this date what it is?" for any early/late/float value, naming the exact predecessor, dependency type, and lag that won, plus every constraint it beat
  • JSON round-tripping for plans (Project.from_json() / Project.to_json())
  • CLI: trueppm-scheduler schedule / trueppm-scheduler monte-carlo

Install

pip install trueppm-scheduler

Requires Python 3.11+.

Quick start

from datetime import date, timedelta
from trueppm_scheduler import schedule, Calendar, Project, Task, Dependency, DependencyType

calendar = Calendar()  # Mon–Fri, no holidays (whole-day scheduling)
task_a = Task(id="t-1", name="Design", duration=timedelta(days=5))
task_b = Task(id="t-2", name="Build",  duration=timedelta(days=10))
dep = Dependency(predecessor_id="t-1", successor_id="t-2", dep_type=DependencyType.FS)

project = Project(
    id="p-1",
    name="My Project",
    start_date=date(2026, 1, 5),
    tasks=[task_a, task_b],
    dependencies=[dep],
    calendar=calendar,
)

result = schedule(project)
build = next(t for t in result.tasks if t.id == "t-2")
print(build.early_finish)  # 2026-01-23 (15 working days from 2026-01-05, across two weekends)

Scheduling granularity. The engine schedules in whole working-day units. Calendar.hours_per_day and Calendar.timezone round-trip through serialization for API parity but are not consumed by the CPM or Monte Carlo passes — they do not change any computed date. Sub-day scheduling is a future change.

Duration and lag are counted in different units

This trips people up, so it is worth stating plainly:

Input Unit
Task.duration (and every PERT estimate) Working days — weekends and calendar exceptions are skipped
Dependency.lag Calendar days — the offset is applied as elapsed time, and only the resulting date is then snapped forward to the next working day

So a 5-working-day task starting Monday finishes Friday, not the following Tuesday. But a 2-day FS lag after a Friday finish does not buy two working days of wait — the weekend absorbs it:

# Predecessor finishes Friday 2026-01-09, Mon–Fri calendar, FS link.
#
#   lag=0d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=1d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=2d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=3d  → successor starts Tue 2026-01-13   (2 working days later)
#   lag=4d  → successor starts Wed 2026-01-14   (3 working days later)

If you need a wait of n working days, size the lag against the calendar the successor will actually land on — or model the wait as a zero-resource task, which is duration-counted and therefore calendar-aware end to end.

Negative lag (lead) is supported and follows the same calendar-day rule: the candidate date snaps forward to the next working day too, never backward. A lead that pulls the candidate into a weekend does not borrow the Friday before it — it lands on the Monday after:

# Predecessor A is 6 working days starting Mon 2026-01-05, so it finishes
# Mon 2026-01-12. FS link, lag=-3 (a 3-day lead).
#
#   candidate = A.finish + 1 day - 3 days = Sat 2026-01-10
#   Sat is non-working, so it snaps forward -> successor starts Mon 2026-01-12
#
# Not Fri 2026-01-09 — the engine never snaps a lead or lag backward.

Per-task calendars

By default every task is scheduled on the single Project.calendar. A task can instead opt into its own working week — useful when one schedule spans teams or projects that keep different calendars:

seven_day = Calendar(working_days=0b111_1111)  # every day is a working day
support = Task(id="t-3", name="Hotfix", duration=timedelta(days=3), calendar_id="ops")

project = Project(
    id="p-1",
    name="My Project",
    start_date=date(2026, 1, 5),
    tasks=[task_a, support],
    calendar=Calendar(),                 # pass-level default (Mon–Fri)
    calendars={"ops": seven_day},        # registry tasks opt into by id
)

Conventions:

  • Duration arithmetic uses the task's own calendar (calendar_id → entry in Project.calendars). A calendar_id of None uses the pass-level Project.calendar. When Project.calendars is non-empty, a calendar_id with no matching entry raises InvalidScheduleInput — a typo is refused, not scheduled on the wrong working week. With no registry (None or empty) a set calendar_id is ignored and the task uses Project.calendar.
  • Lag on a dependency edge is applied as calendar days (above) and then snapped on the successor's calendar: the constraint lands where the wait is actually consumed.
  • It is fully backward compatible — a project with no calendars registry schedules byte-for-byte as before.
  • Both passes honor them: the CPM schedule() pass (early/late dates, float, criticality) and monte_carlo(). A fully deterministic mixed-calendar project simulates to precisely its CPM finish date, so the two agree by construction.

See the full documentation for CPM output fields, Monte Carlo usage, and CLI reference.

Explaining a result

The CPM pass picks the max (forward) or min (backward) of several candidate constraints for each date, then moves on — it doesn't remember which one won. derive_value() replays that decision for a single task and value, and names the constraint that actually set it:

from trueppm_scheduler import derive_value, Quantity

d = derive_value(project, task_id="t-2", quantity=Quantity.EARLY_START)
print(d.value, d.binding.kind, d.binding.source_task_name, d.binding.dep_type)
# 2026-01-12 predecessor_fs Design FS — Build starts when Design finishes on an FS link

for c in d.contributions:
    print(c.kind, c.source_task_name, c.is_binding)  # every constraint considered, winner flagged

This is what lets a UI (or an AI agent) answer "why is this task starting on the 17th?" with the actual dependency instead of a guess — the value returned is computed the same way the engine computed it, not re-derived heuristically.

Mixing agile and waterfall in one schedule

Real programs are rarely pure CPM or pure Scrum. A task can opt into sprint-based uncertainty instead of a three-point estimate:

from trueppm_scheduler import DeliveryMode, Task

sprint_work = Task(
    id="t-4",
    name="Checkout redesign",
    duration=timedelta(days=10),      # fallback if delivery_mode is later cleared
    delivery_mode=DeliveryMode.SCRUM,
    story_points=21,
)

project = Project(
    ...,
    tasks=[task_a, task_b, sprint_work],
    velocity_samples=[18, 22, 15, 24, 19],  # the team's last five sprints
)

monte_carlo() then samples sprint_work's duration from how many sprints the team's own velocity history says 21 points takes — not from a PERT guess nobody on the team would stand behind — while every other task in the same run still uses its three-point estimate. DeliveryMode.WATERFALL (the default) is unaffected; mixing modes is opt-in per task.

Interpreting the output

The two entry points answer different questions, and their outputs are not the same kind of thing. Reading a schedule() date as if it were a commitment is the single most common way to misuse this library.

schedule() returns one date, and it is the optimistic one. The CPM finish is the earliest feasible completion — the date you get if every task takes exactly the duration you estimated, no task slips, and no risk fires. It is a point on a distribution, not the distribution. Nothing about the forward pass makes that point likely; it is simply the arithmetic consequence of the numbers you fed it.

monte_carlo() returns the distribution that date sits in. Sampling each task's duration and re-running the network thousands of times produces the range of finishes the plan can actually deliver:

Percentile Reading Use it for
p50 Half the simulated runs finished on or before this date. In practice it lands close to the CPM finish. A midpoint, never a commitment
p80 4 in 5 runs finished by this date. The commitment date — internal and stakeholder plans
p95 19 in 20 runs finished by this date. Contractual deadlines, launch dates, regulatory submissions

So a CPM finish of 2026-03-03 and a P80 of 2026-03-14 do not disagree. They say: the plan can finish on March 3, and it will finish by March 14 four times out of five. Committing to March 3 is committing to a coin flip.

Two consequences worth internalizing:

  • A task with no three-point estimate contributes no uncertainty. It uses its fixed duration on every run, so a project where nothing is estimated simulates to precisely the CPM finish — p50 == p80 == p95. That is a correct result, not a broken one: you asked what varies, and the answer was nothing. Add optimistic/most-likely/pessimistic values to the tasks that drive the date (MonteCarloResult.sensitivity ranks them) to get a real band.
  • Widening the band is not pessimism. A pessimistic estimate set to most_likely × 1.2 produces a distribution too narrow to be useful — PERT derives σ as (P − O) / 6, so a P barely above M encodes near-certainty. The P value should describe a realistic bad day.

The same framing, with the underlying math, is in the Monte Carlo documentation.

Scope. Only this package's Python engine runs Monte Carlo. The companion Rust/WASM engine (trueppm-wasm-scheduler, used for browser-side and offline recompute) implements the deterministic CPM pass only — there is no probabilistic path there to keep in conformance.

Both engines are tested against each other and, separately, against an independent reference CPM written from the conventions below. The fields that comparison covers exactly, and the ones it does not, are listed in CONTRIBUTING.md.

Conventions

Every modeling rule the engine commits to, one line each, with the issue or ADR that decided it. Differs marks the rules where a schedule built in MS Project or Primavera P6 can come out differently here; everything else follows their convention. The same list, with the comparison spelled out, is on Scheduler Conventions.

Units and calendars

  • Durations and three-point estimates count working days, in whole days only; a sub-day duration or lag raises InvalidScheduleInput. Differs — both tools schedule in hours. (#826)
  • Calendar.hours_per_day and Calendar.timezone are inert — they round-trip and change no date. Differs. (#4131)
  • Lag counts calendar days; the resulting date always snaps forward to the successor's next working day — a lead (negative lag) follows the same rule and never snaps backward. Differs — MS Project and P6 count lag in working time by default. (#2534; open question #2535)
  • Per-task calendars: duration expands on the task's own calendar, lag is consumed on the successor's. (ADR-0120)

Links and constraints

  • An FF/SF-driven task stays contiguous and right-aligned on its pinned finish, so its start moves back — the MS Project convention. Consequence: CPM is non-monotone in duration on an FF/SF network (a longer task can start earlier). (#3806, decided: keep)
  • A zero-lag FF and a zero-lag SS on a whole-day Standard calendar reproduce the Start/Finish MS Project itself computed and saved for the same tasks — confirmed against a real MS Project export (LinkTypes.mpp), not just the documented rule. (#4323)
  • An SF link finishes the successor at the start of the predecessor's start day — with zero lag, its last working day is the day before. A positive lag counts from the predecessor's start itself, so a weekend just before it cannot absorb the lag (a Monday start with SF+2d finishes the successor Tuesday); a lead counts back from the zero-lag finish. Verified for the zero-lag, ordinary-work case against a real MS-Project-saved schedule (tests/fixtures/msproject/link_types_2013.py, whose SF predecessor starts on a Tuesday), and now for a positive lag against four independently-corroborated MS-Project-saved alignments (tests/fixtures/msproject/task_links_cross_version.py, #4327) — including the Monday-start, weekend-adjacent-anchor case #4333 reports: all four agree with MS Project, confirming the #4333 fix against external file evidence rather than only the hand-built regression test in tests/test_sf_from_work.py. A second, separate divergence remains (#2534): the engine counts lag in calendar days and snaps forward once, so a lag long enough to reach a second weekend from the anchor again finishes one working day short of MS Project — confirmed on all four alignments by raising their lag past what the saved files actually used (e.g. the Monday-start case agrees through lag=6 and diverges again at lag=7; a mid-week start diverges as early as lag=3). An SF link out of a milestone remains unverified — no MS Project sample found covers it (#4327). (#4145, #4322, #4333, #2534)
  • A task with an SF link may be placed before the project start: its project-start floor is the earlier of the project start and its SF placement, which its SF links already enforce, so the project start never holds it back, and a binding FS, SS or FF lead can also place it there. A task with no SF link keeps the floor, so its leads stay floored. The data date, planned_start and a recorded actual_start hold every task. A shorter lag never finishes work later; on a network of tasks with work, an FS, SS or FF link that does not bind moves nothing. MS Project's behavior for mixed links and for leads is unverified (#4319). (#4218, #4220)
  • A zero-duration milestone is an instant: at the end of its driver's finish day, or the start of the day a floor holds it to. A lag, or a predecessor's recorded finish on a non-working day, that places it after a weekend or holiday shows it at the start of the next working day — confirmed for the work-driven case against a real MS Project export with all 10 zero-duration milestones in a saved .mpp chain. The project start only bounds the day a milestone is shown on: a milestone that a lead or an SF-placed predecessor puts before it is shown on the project's first working day (unless it has an SF link of its own), but its successors' lags count from the earlier point — unverified against MS Project or P6 (#4225). Its start and finish are one instant, so an FF link into a milestone places it exactly where FS does, a lagged SF link places it on its anchor plus the lag (a positive lag counts from the predecessor's start itself), and an FF link out of it measures a positive lag from that instant; with no lag or a lead it counts from the end of the working day before the milestone, so a longer lead never finishes the successor later. (#4079, #4173, #4225, #4272, #4273, #4323)
  • The only date constraint is start-no-earlier-than, via planned_start; planned_finish is reserved and inert — no deadline, finish, must-start-on or ALAP constraint. Differs. (#3345, #804)
  • An SS or SF link from a summary task is rejected (FS/FF from a summary expand to its leaves). Differs — MS Project accepts it. (ADR-0370)

Progress and actuals

  • A completed task (actual_finish set, or 100%) is pinned to its recorded dates verbatim — even on a non-working day — and is never re-sampled. With no recorded actuals it is pinned at the project start (or its planned_start, when later); no predecessor moves it. A completed milestone stays an instant: with no actuals at the start of its pinned day; with actuals on its recorded actual_finish (else actual_start) day, at the edge of that day it had live — the end when completed work finishing that day placed it, or — while a predecessor is still open — when Task.live_day_end_on (the day your previous run showed it at the end of) names that day; otherwise the start. No change to open work moves it, and when you pass your previous run's output back, closing it on its forecast day moves no successor (#4433, #4525). (ADR-0136)
  • An in-progress task schedules its remaining duration − floor(duration × pct / 100) working days forward from the data date (status_date), floored at its unsnapped actual_start. (ADR-0132)

Float and output

  • is_critical is exactly total_float == 0; total float is the working days from early to late start.
  • free_float inverts the forward constraint across all four link types, capped at total float; no live successor → total float. (#1828)
  • The order of ScheduleResult.tasks is unspecified — look tasks up by id. (#1862)
  • project_finish and a milestone's early_finish are the day the finish is shown on, and milestone_at_day_end says which edge of it. The end of a Friday and the start of the next Monday are the same point in working time, so the shown day can hop a weekend or holiday with no working-time move. Compute slip in working time, reading a start-of-day milestone finish as the end of the working day before it — never as a calendar-day difference of two finishes. (#4178)
  • The same holds for Monte Carlo: MonteCarloResult.p50/p80/p95 are shown days, and p50_at_day_start/p80_at_day_start/p95_at_day_start say which edge of each. Compare a percentile with the CPM finish, or with another run's percentile, in working time. (#4204) These are read-only properties over MonteCarloResult.percentiles, a dict[int, Percentile] of the levels that were computed (Percentile(date, at_day_start)), so result.percentiles[80].date equals result.p80. (#4514)

Monte Carlo

  • Three-point estimates sample a Beta fitted by method of moments to the classic PERT mean (O + 4M + P) / 6 and σ = (P − O) / 6 — not the λ=4 Beta-PERT. Same mean; on a symmetric estimate the band is ~12% narrower (P80/P95 slightly earlier), on one whose mode sits at an end it is wider. Differs from @RISK's default. (ADR-1245, #4133)
  • Every sampled duration is floored at Task.duration — the optimistic tail below the plan is not expressed. Differs — risk tools sample the whole estimate. (#3765)
  • "Never before the CPM finish" holds only on FS/SS-only networks; on an FF/SF network a percentile can land earlier, because CPM itself is non-monotone there. (#3806)
  • A fixed seed reproduces P50/P80/P95 on the same numpy and trueppm-scheduler versions — see Reproducibility. (#4099)

Errors and input limits

Every exception the engine documents raising subclasses ValueError (via the common SchedulerError base), so one except ValueError catches them all — but each is individually catchable:

Exception Raised when
CyclicDependencyError The dependency graph contains a cycle. .cycle lists the task IDs forming it.
SimulationCapExceeded monte_carlo(runs=…) exceeds max_runs, or the project has more tasks than max_tasks.
InvalidScheduleInput The input is structurally valid but out of range, or the wrong type (see below).
UnknownTaskError derive_value(project, task_id, …) is called with a task_id that names no task in the project.

What this guarantee actually covers. Project.from_dict() / Project.from_json() — the untrusted-input path — type-check and coerce every field, so a malformed document of any shape raises InvalidScheduleInput and never a bare AttributeError/TypeError. Constructing Project/Task/Dependency directly in Python (the direct-object API, as in every example above) is held to the same field rules from_dict() applies, on every field of Project, Task, Dependency and Calendar — including the fields the engine never reads: the reserved Calendar.hours_per_day (a finite number) and timezone (a string), the computed task dates (early_start … scheduled_start, plain date or None) and floats (total_float/free_float, timedelta), the is_critical and milestone_at_day_end flags (bool), and delivery_mode (a DeliveryMode or None, not the string "scrum"). Calendar.working_days must be an integer in [0, 127], and a calendars registry must be keyed by string ids. A wrong-typed or out-of-range value (None, a string, a datetime, a bare int where a list or timedelta is expected, an unhashable value, …) makes schedule() and monte_carlo() raise InvalidScheduleInput, not a bare Python exception. (derive_value() applies the same check when it schedules the project itself, i.e. when called without result=.)

So any project schedule() accepts round-trips: Project.from_json(p.to_json()) loads it back unchanged and schedules it identically. to_dict() and to_json() on Project (and to_dict() on Task, Dependency and Calendar) apply the same rules and raise InvalidScheduleInput for a field they cannot serialize. Construction itself stays lenient — the check runs when a project is scheduled or serialized, so an object can be built partially and filled in first. tests/test_exception_contract.py pins the per-field guarantee with a single-field-mutation sweep over the init fields × 12 adversarial values × both schedule()/monte_carlo() entry points (Task.id is excluded from that sweep; a non-string task id is covered by the explicit examples in tests/test_contract_fuzz.py), and tests/test_roundtrip_contract.py property-tests the round trip, so a future field addition that reopens a gap fails a test rather than becoming a silent leak.

The engine walks the working calendar one day at a time, so it also validates input up front rather than spinning on a degenerate project:

  • Calendar — working_days must be an integer bitmask in [0, 127] that sets at least one weekday bit (Mon–Sun); a calendar whose exceptions blanket the entire search window is rejected too.
  • Duration — each task duration must be between 0 and MAX_DURATION_DAYS (36_525, ~100 years). Negative durations are rejected.
  • Lag — each dependency lag must be within ±MAX_LAG_DAYS (36_525).
  • Project span — the cumulative span (every task's worst-case duration plus the magnitude of every lag) must stay under MAX_PROJECT_SPAN_DAYS (366_000, ~1000 years), regardless of task count.
  • Monte Carlo — runs must be >= 1.

Project.from_json() also rejects the non-standard JSON literals NaN, Infinity, and -Infinity.

from trueppm_scheduler import schedule, InvalidScheduleInput

try:
    result = schedule(project)
except InvalidScheduleInput as e:
    print("Bad input:", e)  # "Task 't-1' duration exceeds the maximum of 36525 days (got …)."

Limits for embedders

The validator caps above are all exported from the top-level trueppm_scheduler package, under the same names the error messages use, so an embedding application can check or re-enforce them without hand-copying a number:

Cap Value Bounds
MAX_DURATION_DAYS 36525 A single task's duration or PERT estimate (~100 years)
MAX_LAG_DAYS 36525 A single dependency's lag, either direction
MAX_PROJECT_SPAN_DAYS 366000 Cumulative project span — every task's worst-case duration plus every lag (~1000 years)
MAX_DEPENDENCIES 100000 Raw dependency-edge count, before summary expansion
MAX_EXPANDED_EDGES 100000 Leaf-level edges after expanding a summary↔summary dependency
MAX_CALENDAR_EXCEPTIONS 100000 Exception ranges on one Calendar
MAX_CALENDAR_SCAN_DAYS 36600 Longest run of consecutive non-working days before a calendar is declared degenerate
MAX_LAG_DELTA_CELLS 50000000 Monte Carlo's (distinct dep-type/lag combos) x (index span) precompute
MAX_VELOCITY_SPRINTS 10000 Per-run sprint horizon the velocity sampler will bootstrap
MC_SENSITIVITY_CAP 20 Tasks returned by the sensitivity ("tornado") ranking
from trueppm_scheduler import MAX_DEPENDENCIES, MAX_DURATION_DAYS, MAX_LAG_DAYS

There is no fixed task-count or run-count cap built into the engine itself — monte_carlo(max_runs=…, max_tasks=…) are opt-in, caller-supplied ceilings that default to None (uncapped). That default is correct for a batch script or notebook that owns the whole machine, and wrong for a synchronous web request: schedule() and monte_carlo() are CPU-bound (a day-by-day calendar walk, plus a numpy-vectorized sampling pass), so a request handler that calls either directly on untrusted or unbounded input ties up a worker thread or process for as long as the input demands. Pass max_runs and max_tasks whenever the caller is untrusted, and run the call off the request thread with a wall-clock timeout — a worker/queue, not inline in the view — the same pattern the TruePPM API itself uses (#4010).

A long calendar exception does not cost more as the dependency graph grows: calendar-day lookups are index-backed (a cached, bisected merged-interval index), so both the CPM pass and Monte Carlo snap to the next or previous working day in O(log E) regardless of how many tasks or dependencies reference that calendar.

API stability and versioning

The public API is the __all__ surface of the top-level trueppm_scheduler package — the names you can import directly from trueppm_scheduler (schedule, monte_carlo, Project, Task, Dependency, DependencyType, Calendar, ScheduleResult, MonteCarloResult, the exception types, etc.). Everything else — the trueppm_scheduler.engine internals, any underscore- prefixed helper, and module layout — is unstable and may move or change without notice.

This package is Development Status :: 4 - Beta as of 0.4.0b1: the public API may still change before 1.0. Pin an exact version rather than a range:

trueppm-scheduler==0.4.0rc1

Beta releases are pre-releases: pip installs a pre-release only when you pass --pre, or when no final release satisfies the requirement yet. PyPI currently holds only pre-releases of trueppm-scheduler (no version has reached final), so today a bare pip install trueppm-scheduler falls into the second case and installs the latest beta. Once 0.4.0 final ships, that changes: a bare install will resolve to 0.4.0 and skip any later 0.5.0 betas unless you pass --pre — which is why pinning an exact version (above) is the reliable approach in either state. Breaking changes are recorded in CHANGELOG.md, which also ships inside the wheel.

Heads-up: trueppm_scheduler.engine becomes a subpackage in 0.5

0.5 will split the single trueppm_scheduler/engine.py module into an engine/ subpackage (CPM, Monte Carlo, calendar math, validation, and so on in separate files). The split is planned to land on main in November–December 2026 and ship with 0.5 (#4550). It is a pure move: scheduling results will not change.

Will keep working, unchanged:

  • Every import from the top-level trueppm_scheduler package (the __all__ surface above).
  • from trueppm_scheduler.engine import X for every name importable today, including underscore-prefixed helpers. engine/__init__.py re-exports them for the whole 0.5 line.
  • Result objects pickled by 0.4 will still unpickle on 0.5.

Will need a change on your side:

  • Patching engine internals in your tests. unittest.mock.patch("trueppm_scheduler.engine._helper") or monkeypatch.setattr(engine, "MAX_DEPENDENCIES", 1) will replace the re-exported name. The code that actually calls the helper or reads the constant will still see the original, so the patch stops taking effect, usually without failing the test. Point such patches at the submodule that defines the name once you upgrade.
  • Code that reads a class's __module__, or tooling keyed on the file path trueppm_scheduler/engine.py (coverage or lint excludes, for example).
  • Result objects pickled by 0.5 will not unpickle on 0.4.

If you depend only on the public API, there is nothing to do.

Reproducibility (seeded runs)

Monte Carlo simulation is reproducible for a fixed seed: the same seed always yields the same P50/P80/P95 forecast for the same input, on the same numpy version and the same trueppm-scheduler version. Within that envelope this is a supported, tested property you can rely on for reproducible reports and regression baselines — not an implementation detail.

Outside it, it is not promised. The dependency range is numpy>=1.26,<3, and numpy guarantees a Generator's random stream (Generator.beta included) only within one release (NEP 19), so upgrading numpy can move seeded percentiles. A trueppm-scheduler release can move them too — a sampling fix or a change to the order tasks are sampled in is recorded in the changelog. If a seeded baseline must stay bit-identical, pin both packages alongside the seed.

This is a statement about repeatability of the sampling, not about the shape of the answer — a seeded Monte Carlo run still returns a probability distribution. Do not confuse it with the deterministic single-date output of schedule(), which is a different thing entirely.

Status and roadmap

0.4 — the current release. The CPM pass (all four dependency types, calendar-aware lag, cycle detection) and Monte Carlo simulation (PERT-Beta, velocity sampling, derive_value() explainability) are stable and exercised by the fuzz, mutation, and MS-Project-parity suites described in CONTRIBUTING.md.

Known limitations open against 0.4, grouped by area — every item below is an open issue; nothing in this list is fixed yet, regardless of which future release it is scheduled for:

  • CPM correctness — while any predecessor of a closed milestone is still open, its frozen day edge (live_day_end_on) reflects the last derivation, so correcting a completed predecessor's actuals or removing a link is not re-read until every predecessor completes (#4574); a work-task late-finish seed can ignore a start-of-day project finish on wider calendars (#4436); FF/SF links into a summary task do not fan out to every leaf the way the successor side does (#4437); perturb_task_duration(duration=0) on a started milestone can mark it complete and move the schedule as a side effect of the perturbation (#4536); driving_edges can omit a link whose calendar-day lag lands on non-working time even though removing it does move the successor (#4537); expand_summary_dependencies can invent a sibling ordering from a summary-to-own-child link that find_cycle correctly flags as a cycle (#4538); a completed task with no recorded actuals can be moved later than the data date, a non-monotonicity where knowing less about a task slips the schedule further than knowing more (#4539); and several MS-Project-parity cases — SF out of a milestone, mixed SF+FS/SS/FF at the project-start floor — remain unverified against a real MS Project export (#4327, #4319).
  • Monte Carlo — a velocity-sampled duration is re-expanded against the task's own calendar rather than the sprint calendar it was sampled against (#4529); sprint-horizon clamping truncates the slow tail of a velocity-driven P80/P95, so it reads as a lower bound rather than a full forecast (#2469); three monte_carlo() keyword caps still leak a bare TypeError instead of the documented SchedulerError contract (#4464); and percentile estimation is imprecise at very low run counts (10–11 runs), where the reported P95 can have only 90% of runs on or before it (#4540).
  • Calendars — a zero-lag milestone-to-milestone link into a narrower per-task calendar can overstate float (#4526).
  • Scale / performance — a project above roughly 73,000 tasks at a 5-day average duration is refused as "longer than 1,000 years" by a span guard meant to catch pathological input, not real large projects (#3830); Monte Carlo holds three (runs × tasks) float64 matrices live in memory, already 2.3 GB at 50,000 tasks (#3824).
  • API contract / errors — the derivation vocabulary (DerivationContribution.kind, Derivation.quantity/pass_) is still an open string, not a published enum (#4291), and exported dataclasses document their fields in source comments rather than Google-style Attributes: sections, so they do not render in a generated API reference (#4471).
  • WASM engine — wasm-scheduler errors are untyped strings at 17 call sites rather than a structured error type (#4474), and the CPM invariant-property suite that fuzzes the Python engine has no Rust port yet, so a Rust-only regression would not be caught the same way (#4270).

Committed for 0.5. 0.5 will run a hardening pass over the engine (#3988) rather than ship new scheduling features; the following are release::committed for 0.5 — they will ship with 0.5 or that release will slip:

  • Engine decomposition and correctness hardening — splitting engine.py into a subpackage without breaking imports (see the heads-up above; #4550) and extending the independent CPM oracle to milestone late dates/floats (#4275); mutation-testing phase 2 brings engine.py itself into scope (#2468); three more bare-exception leaks close the SchedulerError contract (#4162, #4132); and the span-guard bug above will be fixed, raising the supported envelope toward 50,000 tasks (#3830, #3825).
  • Performance — a published pytest-benchmark suite at 100–5,000 tasks, with measured numbers in this README (#4230); the Monte Carlo memory footprint above is chunked over runs and dropped to float32 (#3824); the CPM duration-expansion day-walk above moves off O(duration) (#1531).
  • Monte Carlo correctness — the sprint-horizon clamp bug above will be fixed (#2469); an in-progress task's sampled duration no longer has its optimistic tail truncated by subtracting deterministic elapsed time from the sampled total (#1495).
  • Scheduling semantics — the calendar-day-vs-working-day lag question will be decided (#2535); deadline-driven negative float will surface "behind committed date" in CPM output (#804); and partial resource allocation (e.g. someone at 60%) will be enforced in the CPM/leveling pass (#84, #744).
  • Packaging — stale/placeholder CITATION.cff metadata (a fake ORCID and DOI) will be corrected (#3857).

May also land in 0.5, but not committed: the velocity-sampled duration re-expansion on the wrong calendar above (#4529), the FF/SF-into-summary fan-out and derive_value() binding/imposed_date mismatch above (#4437, #4438), the remaining MS-Project-parity gaps, the zero-lag milestone-calendar overstatement (#4526), the three leaking Monte Carlo keyword caps, a monte_carlo(return_samples=True) option to hand back the raw matrices (#4166), and five findings from the 2026-10-18 scheduler audit above: the perturb_task_duration milestone side effect (#4536), the driving_edges false negative on calendar-lag-onto-non-working-time (#4537), the expand_summary_dependencies sibling-ordering bug on invalid input (#4538), the completed-task-without-actuals non-monotonicity (#4539), and Monte Carlo percentile imprecision at very low run counts (#4540).

Later — a sequence, not a schedule. Versions past 0.5 carry no date; what ships and in what order is set by evidence from the 0.4 beta and 0.5, not by this list (full rationale on the roadmap). 0.6 will open the write surface safely — an engine-as-referee that will refuse any agent write which would create an impossible schedule, building on the 0.5 plan-mode dry run — and will start the hybrid human/AI engine depth begun in 0.5: sub-day scheduling, an explicit effort-vs-duration split, and a probabilistic human-fallback branch for agent-delivered work. 0.6 is also planned to bring the OSS resource-leveling pass: CPM assumes infinite resources today, and leveling will resolve the conflicts the 0.5 pre-commit warning only flags. 0.7 is planned to bring resource-constrained Monte Carlo once the sampler's own correctness checks are in place, Rust/WASM leveling parity, and probabilistic branching (conditional paths sampled per run). 0.8 is planned to add task splitting (interruptible, resumable duration).

Security

Found a vulnerability in the scheduling engine? Please report it privately — do not open a public issue. Email security@trueppm.com or open a confidential GitLab issue. Full policy, response SLAs, and safe-harbor terms are in SECURITY.md at the monorepo root.

License

Apache 2.0

Metadata

Release files for trueppm-scheduler 0.4.0rc1

For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.

Source distribution (sdist)

Source distribution for trueppm-scheduler 0.4.0rc1
File Size Uploaded Provenance Actions
trueppm_scheduler-0.4.0rc1.tar.gz 484.9 kB With provenance Details for trueppm_scheduler-0.4.0rc1.tar.gz

Built distribution (wheel)

Table of built distributions (wheels) for trueppm-scheduler 0.4.0rc1
File Interpreter ABI Platform Actions
trueppm_scheduler-0.4.0rc1-py3-none-any.whl Python 3 none any Details for trueppm_scheduler-0.4.0rc1-py3-none-any.whl

Total release size: 680.4 kB

Release files / trueppm_scheduler-0.4.0rc1.tar.gz

Download URL trueppm_scheduler-0.4.0rc1.tar.gz
Size 484.9 kB
Tags Source
SHA-256 checksum
How to use checksums
299c34f724ae2f11c31001b1615af4c03c0350eb4b39c3e87a9e5deee31dfd5a
BLAKE2b-256 checksum
How to use checksums
ad8abc9ddcd42d1fec0cfc50f8cb7e47b084e3ce5ccfe3efcddf94537ce0c370
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
Yes
Uploaded via twine/7.0.0 CPython/3.11.15

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

PyPI Publish Attestation

PyPI verified that this artifact, at this checksum, originated from the publisher listed below.

Signed by GitLab CI/CD, verified by PyPI on Oct 20, 2026.

Transparency log

Release files / trueppm_scheduler-0.4.0rc1-py3-none-any.whl

Download URL trueppm_scheduler-0.4.0rc1-py3-none-any.whl
Size 195.5 kB
Tags Python 3
SHA-256 checksum
How to use checksums
53d056be9b5b29ae8774aec119f9804c940575d98d51d4113810c7a6dc9e3e61
BLAKE2b-256 checksum
How to use checksums
6f86854ab0290761250bb92ae6bf3eb6b08327e8e8a5cc8ac737f6b0f3da0716
Upload date
Uploaded using Trusted Publishing?
What is trusted publishing?
Yes
Uploaded via twine/7.0.0 CPython/3.11.15

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

PyPI Publish Attestation

PyPI verified that this artifact, at this checksum, originated from the publisher listed below.

Signed by GitLab CI/CD, verified by PyPI on Oct 20, 2026.

Transparency log

Security for trueppm-scheduler 0.4.0rc1

Provenance

Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.

Full provenance

Both files in this release have been uploaded with provenance metadata.

Select from 2 files

Attestation for trueppm_scheduler-0.4.0rc1.tar.gz

PyPI Publish Attestation

PyPI verified that this artifact, at this checksum, originated from the publisher listed below.

Signed by GitLab CI/CD, verified by PyPI on Oct 20, 2026.

Transparency log

A note on package security

PyPI is a repository for distributing packages, not a service for auditing them. While third-party security researchers and our staff do their best to detect and remove malicious packages, PyPI cannot guarantee the quality, security or suitability of any given package.

To learn more about protecting yourself from malicious actors, visit our package security documentation.

Anthropic, PBC Visionary sponsor Bloomberg Visionary sponsor Hudson River Trading Visionary sponsor Meta Visionary sponsor NVIDIA Visionary sponsor Microsoft Sustainability sponsor Depot Continuous Integration AWS Cloud computing and Security Sponsor Datadog Monitoring Fastly CDN Google Download Analytics Sentry Error logging StatusPage Status page