Project Planner
A small planning system that lets you define project plans and tasks in YAML or Python. Validate plans, inspect funding and dependencies, and export Word plans, SVG diagrams, and fiscal-month Gantt charts in SVG or editable PowerPoint format.
Repository: git@re-git.lanl.gov:tpp/planner.git
Installation
Use Python 3.11 or newer.
Install from PyPI
If you only want to use the planner, create and activate a virtual environment and install the published package. No repository checkout is needed:
python3 -m venv .venv
source .venv/bin/activate
python -m pip install tuxfan-planner
planner --help
This installs the planner and its required Python dependencies. Activate .venv
again when starting a new shell. To get started with your own plan, follow
Your first plan below.
Install from source
For development or to use a local checkout, run these commands from the repository root:
python3 -m venv .venv
source .venv/bin/activate
python -m pip install -e .
planner --help
The editable installation uses the source in this checkout. CMake installation and development setup are described in DEVELOPER.md.
Quick start
From the repository root, validate the fictional example plan, list its tasks, and export a Word document:
planner validate data/tasks.yaml
planner list tasks data/tasks.yaml
planner export data/tasks.yaml /tmp/plan.docx --export-options planner/examples/export-options.yaml
The output file is written to /tmp/plan.docx. For other outputs, see
Exporting.
data/tasks.yaml is the canonical fictional jet-airplane
development fixture. data/composite.yaml includes the
same plan. Their values are invented; use them instead of private plans for
future development. See the fixture guide for coverage and
examples.
Contents
- Installation
- Quick start
- Basic commands
- Your first plan
- Plan structure and fields
- Viewing and filtering
- Exporting
- Advanced plan authoring
- Configuration and optional tools
- Troubleshooting and further documentation
Basic commands
| Command | Purpose |
|---|---|
validate |
Check a plan and report validation statistics. |
list KIND |
Show concise task details grouped by activity. |
list-detail |
Show full task details. |
show |
Print unique values used by one field in a plan. |
avail |
Print predefined schema options for one field, without a plan. |
fields |
Print a copyable YAML template for a mapping type. |
summary |
Show counts by execution section and milestone, plus funding totals. |
schedule |
Show tasks in dependency order and their readiness. |
export |
Write a Word (.docx) or SVG (.svg) plan. |
export-gantt |
Write an SVG or PowerPoint (.pptx) Gantt chart. |
composite |
Expand YAML includes into a standalone file. |
merge |
Merge standalone YAML tasks into a multipart task. |
split |
Split a multipart YAML task into standalone tasks. |
format |
Format a YAML or Python plan with an optional external formatter. |
spell-check |
Review prose interactively with Aspell. |
completion |
Generate a shell completion script. |
Run planner COMMAND --help for arguments and examples, or see the
CLI reference.
The legacy tuxfan-planner command remains available as an alias.
Run planner --help to see the current package version and the current values
of all planner environment variables alongside the command help.
Your first plan
Save this as tasks.yaml. It defines one pending task with a two-month duration:
project: Aircraft Development
tasks:
- id: DraftDesign
label: Draft aircraft design
description: Produce the initial airframe design.
start: M1Q1FY27
expected: 2
priority: high
status: pending
risk:
- type: schedule
level: low
mitigation: Review progress weekly.
planner validate tasks.yaml
planner list tasks.yaml
id identifies the task for dependency references; label is its display name.
execution_section links tasks to the corresponding entry in execution.sections. Tasks without a link appear under Unassigned. The top-level project names the overall plan. start is a
fiscal period, and expected counts months including the start month. This task
runs from October through November 2026. priority, status, and risk describe
the planned work. Ongoing and completed tasks have exceptions to the planning
field requirements, explained below.
Fiscal period values
start and completed must use M{month}Q{quarter}FY{year}:
monthis1to3within the quarterquarteris1to4yearis a 2-digit fiscal year, for exampleFY26
Fiscal years begin on October 1:
Q1= October through DecemberQ2= January through MarchQ3= April through JuneQ4= July through September
Examples:
M1Q1FY26= October 2025M2Q3FY26= May 2026M3Q4FY26= September 2026
Duration and completion
Task dates use start plus expected. For example:
start: M3Q4FY26
expected: 2
This task spans M3Q4FY26 through M1Q1FY27. A duration of 1 stays in the
start month. Compact completed tasks may omit both scheduling fields; they use completed as the start and a
one-month duration.
Status values
Use one of:
pendingplanningactiveongoingblockedunfundedcompleteclosed
Plan structure and fields
A plan can be a raw task list or a mapping containing tasks and optional
plan metadata. Start with the mapping form shown above.
Plan metadata
A plan can include optional top-level project metadata:
portfolio: portfolio or parent program name.project: high-level project name.managers: list of manager names.pocs: list of point-of-contact names.summary: high-level plan summary.fiscal_range_beginandfiscal_range_end: optional fiscal year range covered by the plan, for example27through31.execution: execution metadata. It can be a mapping withoverviewtext andsections, where each section haslabel,description, and an optional stableidfor task links. The older flat list of sections is still accepted.
Planning placeholders
Use status: planning to add a task before its schedule, priority, and risks
are known. Only four fields are required:
tasks:
- id: FUTURE_DESIGN
label: Future design work
description: Scope and deliverables to be developed.
status: planning
Add optional fields as the plan develops. Supplied values are validated normally;
omitted priority defaults to low and risks to an empty list. A start or duration
may be supplied individually, but timing remains Unscheduled until both start
and expected exist. Unknown duration displays as Unspecified. With both fields,
normal month-based timing applies, including a provisional Gantt bar. Undated
placeholders sort after dated tasks.
Funding estimates contribute to totals without creating dates or full-year bars
(as they do for ongoing). Dependencies are allowed, but planning tasks do not
satisfy dependencies and always show PLANNING in the schedule. Lists and exports
retain placeholders; Word narratives mark them [PLANNING]. Changing to an
execution status enforces its usual required fields.
Closed tasks are marked [CLOSED] in gray in Word narratives.
Closed tasks require only id, label, description, and status: closed
and display CLOSED in schedules. Execution section, timing, priority, and risk are optional;
supplied values are validated. Without both start and expected, timing remains
Unscheduled and no Gantt bar is drawn. They use the same gray styling as unfunded tasks. Valid choices from
planner avail status and generated templates list closed last.
YAML plan and export-option files reject duplicate explicit keys with source
locations. Explicit entries may still override values inherited through << merges.
Task fields
Tasks use only execution_section for grouping and funding for budgets. The
optional Funding export column calculates the sum of a task's fiscal-year amounts;
parent budgets retain the existing count-once rule in plan totals. Top-level
project remains the overall plan title. Every unknown key is an error at its
source location, including task/part keys, nested metadata, and export options.
There are no special diagnostics or compatibility aliases for removed fields.
Each task supports these fields. start, expected, priority, and risk
are optional for closed tasks, planning placeholders,
ongoing tasks, and complete
tasks with a completed period:
id: required non-empty string task id (quote numeric IDs). Must contain only letters, numbers, or underscores, with no spaces.label: required non-empty string display name for the task.site: optional site or institution label.bnr: optional budget and reporting identifier.type: optional task type label.tags: optional comma-separated string or list of task tags. Omitted or null values mean no tags.execution_section: optional ID of a section underexecution.sections. Linked tasks use that section's label and position for activity headings and task numbers in exports. An unknown ID is rejected.description: required non-empty string describing the task.note: optional string with additional task information. Unrecognized keys are rejected uniformly.workitems: optional GitLab work item or merge request references; see Work item references.start: required fiscal period string inM{month}Q{quarter}FY{year}format, wheremonthis1to3within the quarter.expected: required positive whole number of months for the task duration. The end month is computed fromstart, counting the start month as month one.completed: optional fiscal period string for work that is already complete. A task withstatus: completeandcompletedmay omit planning-only fields:start,expected,priority, andrisk. A complete task withoutcompletedstill requires these fields.milestones: optional list of milestone IDs, for example[Design, Implementation]. Every ID must match a top-level milestone definition. Omitted/null values or an empty list mean no milestones.priority: required string priority label such aslow,medium,high, orurgent.status: required string status. Allowed values arepending,planning,active,ongoing,blocked,unfunded,complete, andclosed. Useunfundedfor work awaiting funding.dependencies: optional list of task ids. Omitted or null values mean no dependencies. Each supplied dependency must reference another taskid.risk: required risk entry or list of risk entries. Each entry hastype,level, andmitigation, and may includedescription;levelmust below,medium,high, orextreme.funding: sole budget input, an optional mapping of fiscal year to funding level, for examplefy27: 50K. A task is treated as unfunded for fiscal years not present in this mapping. For tasks other thanongoing, a warning is issued when a funding year falls outside the fiscal years covered by the task'sstartand calculated end month.
Omitted dependencies and tags are empty collections internally. Outputs that
need a value display None, including dependency fields in list-detail and
schedule, SVG dependency text, and an explicitly selected Tags table column.
The concise list output continues to omit empty Dependencies lines.
Milestones
Define milestones at the top level with id, label, description, and a
fiscal deadline. deliverables is an optional list of IDs referencing
top-level deliverable definitions. Omitted/null/empty lists mean no references. IDs must be unique and use letters, numbers, and underscores.
Tasks can omit milestones; every supplied ID must be defined, including links
inherited by multipart tasks. Task files without milestone references need no section.
Milestone deadlines do not change task durations or dependency scheduling.
Summary counts include a task under each of its milestones. Duplicate task milestone IDs are counted once. CLI metadata and Word output include milestone definitions; plan SVG headers summarize milestone labels and deadlines. Word and SVG exports display milestone labels without IDs.
Deliverables and deadline checks
Define outputs in a top-level deliverables list. Each entry requires id,
label, description, and type. IDs use letters, numbers, and underscores;
types are paper, document, presentation, or release (trimmed and normalized to
lowercase). A document is material such as internal documentation that does not
require submission, unlike a paper intended for submission. It can be marked
complete directly; no submitted step is required. Additional types are added
in code, not through plan configuration.
deliverables:
- id: RESULTS
label: Results paper
description: Reviewed manuscript describing the results.
type: paper
milestones:
- id: REVIEW
label: Program review
description: Results available for review.
deadline: M3Q2FY27
deliverables: [RESULTS]
tasks:
- id: WRITE
label: Prepare manuscript
description: Analyze and write up the results.
status: planning
start: M1Q2FY27
expected: 3
deliverables: [RESULTS]
A task's optional deliverables list identifies its outputs. Every task
referencing a required output is a required producer. References are trimmed and
deduplicated; omitted/null/empty means none. Multipart parts inherit the list
and may replace or clear it. All task and milestone references must resolve.
For a required deliverable, readiness is the latest finish of all its producers. Its required-by date is the earliest deadline of milestones requiring it. Each task must finish by every milestone it cites and every milestone requiring one of its required outputs. Completion in the deadline month is allowed. These constraints produce warnings; they never move tasks, add duration/funding, or change dependency readiness.
Explicit completed dates on complete tasks supply actual timing; other finish
dates are forecasts. An undated or closed producer keeps output readiness
unknown. Ongoing task forecasts use the final funded month; use a separate dated
task when an output is due before ongoing work ends. A required output without
producers also produces a warning. All producers being complete means inferred
complete, not submission or acceptance. Separate draft and final outputs if
milestones require different versions.
Deliverables accept an optional status:
| Status | Meaning | Effect |
|---|---|---|
required |
Committed output; default when omitted | All producer and deadline checks apply |
planning |
Output is still being planned | Defer assessment through this output |
blocked |
Required output has an obstacle | Retain all producer and deadline checks |
submitted |
Delivered for review; awaiting acceptance | Remain outstanding and retain all producer and deadline checks |
complete |
Output has been delivered and considered fulfilled | Satisfy its requirement independently of producer states |
closed |
Output is no longer required | Remove its requirement while retaining the record |
Status values are trimmed and normalized to lowercase; explicit null/empty or unknown statuses are invalid. Planning and closed outputs do not acquire a readiness or required-by date. Producer references remain visible for history. Filtering and summary relationship counts retain these historical links; they do not indicate outstanding obligations. Direct task-to-milestone requirements, task dependencies, and requirements through other outputs still apply. Structural validation (including all references and required definition fields) always applies, regardless of status.
A complete deliverable may record an actual completion period:
- id: RESULTS
label: Results paper
description: Reviewed manuscript describing the results.
type: paper
status: complete
completed: M3Q2FY27
completed requires explicit status: complete and a valid fiscal period.
Completion after a milestone deadline produces a historical timing warning;
completion during that month is allowed. Without completed, the output still
satisfies its requirement and displays "completion date unknown", without
borrowing a producer's forecast or issuing missing-producer/timing warnings.
Producer completion can still yield inferred complete for a required output,
but never changes its stored status. Marking an output complete does not complete
its producer tasks. Blocked and submitted outputs retain the same producer and
deadline constraints as required outputs. Completed producers do not imply that
a blocked output is unblocked or a submitted output is accepted; their explicit
states remain authoritative. complete means delivered and considered fulfilled,
including acceptance when that is required. completed remains exclusive to
complete; no submission date is recorded in this version.
validate counts definitions and warnings; list-detail, summary, and plan
exports show outputs and derived timing. list ... deliverables,
show ... deliverables.type, show ... deliverables.status, fields deliverable,
avail deliverables.type, and avail deliverables.status
help inspect and author them. --only deliverables=ID also accepts a label;
milestone filters and summary counts include indirectly linked producers.
Filtered detail output retains readiness computed from all producers.
Migration: milestone deliverables formerly contained prose. Move each
item into a top-level definition and replace milestone text with its ID. Unknown
references are errors; legacy prose is not silently accepted.
Work item references
workitems: optional mapping or list of mappings, each requiring id as a GitLab project-path reference such as aircraft/design#42 or aircraft/design!69. The path must include a namespace and project (nested subgroups are accepted), using ASCII letters, digits, underscores, dots, and hyphens, with each segment starting with a letter or digit. A positive decimal item number follows # (work item) or ! (merge request). Surrounding whitespace is trimmed. IDs are server-relative references, not URLs; no server or item-existence lookup is performed. Explicit type is rejected; the Python API derives WorkItem.type as workitem or mr.
Each entry also accepts status: open (the default when omitted) or closed, trimmed and normalized to lowercase. Explicit null or other statuses are rejected. CLI and configured exports display the status.
Optional assignees accepts a list of non-empty moniker strings, trimmed with case and order preserved. Omitted, null, or empty lists mean no assignees. CLI and configured exports display assigned monikers.
Optional label is a display name, trimmed with omitted/null values becoming empty strings; non-string values are rejected. Labels appear before work item identifiers in CLI and configured exports and support inline Markdown in Word/SVG.
Optional description is prose text, trimmed with omitted/null values becoming empty strings. Descriptions appear with the reference in CLI output and configured exports, where the task-description inline Markdown subset is supported.
Omitted, null, or empty lists mean no references. Multipart parts inherit the parent's references unless they replace or clear them. References appear in list-detail and schedule attributes; select workitems in export options for a Word column or SVG card attributes.
For example, a task can reference a merge request and an issue:
workitems:
- id: aircraft/design!59
label: Solver update
status: closed
assignees: [designer_one, designer_two]
description: Review solver changes.
- id: aircraft/assembly#12
status: open
YAML format
Top-level can be either a list of tasks or a mapping with a tasks key. The mapping form can also include plan-level metadata such as portfolio, project, managers, pocs, summary, fiscal_range_begin, fiscal_range_end, and execution.
portfolio: Advanced Simulation and Computing
project: Task-Parallel Project
managers:
- Alice Example
pocs:
- Casey Example, PI
summary: >
High-level planning context for the task collection.
fiscal_range_begin: 27
fiscal_range_end: 29
execution:
overview: >
Overall execution context for the plan.
sections:
- id: deliverable_a
label: Deliverable A
description: >
Narrative execution detail for this deliverable.
deliverables:
- id: ARCHITECTURE
label: Architecture document
description: Reviewed architecture document.
type: paper
- id: PARSER
label: Parser
description: Released parser implementation.
type: release
milestones:
- id: Design
label: Design
description: Complete the architecture draft.
deadline: M2Q3FY26
deliverables: [ARCHITECTURE]
- id: Implementation
label: Implementation
description: Deliver the task parser.
deadline: M2Q3FY26
deliverables: [PARSER]
- id: Phase_A
label: Phase A
description: Complete the first phase.
deadline: M3Q2FY27
deliverables: []
- id: Phase_B
label: Phase B
description: Complete the second phase.
deadline: M3Q4FY28
deliverables: []
tasks:
- id: DraftArchitecture
label: Draft architecture
bnr: EXAMPLE-001
site: Example Works
type: labor
tags:
- architecture
execution_section: deliverable_a
description: Produce the first architecture draft.
start: M1Q3FY26
expected: 2
milestones: [Design]
priority: high
status: complete
dependencies: []
risk:
- type: scope
level: medium
description: Integration requirements may change during implementation.
mitigation: Review the architecture with stakeholders before implementation starts.
funding:
fy27: 50K
fy29: 100K
- id: BuildParser
label: Build parser
description: Load task definitions from YAML and Python files.
start: M2Q3FY26
expected: 1
milestones: [Implementation]
priority: high
status: pending
dependencies:
- DraftArchitecture
risk:
- type: integration
level: medium
mitigation: Add schema validation tests for both YAML and Python task sources.
- id: MultiYearDelivery
label: Multi-year delivery
site: Example Works
parts:
- id: A
label: First phase
funding: {fy27: 50K}
description: Complete the first phase.
start: M1Q1FY27
expected: 6
milestones: [Phase_A]
priority: high
status: active
dependencies: []
risk:
- type: schedule
level: low
mitigation: Review progress monthly.
- id: B
label: Second phase
funding: {fy28: 100K}
description: Complete the second phase.
start: M1Q3FY27
expected: 18
milestones: [Phase_B]
priority: medium
status: pending
dependencies:
- A
risk:
- type: technical
level: medium
mitigation: Keep integration tests current.
Viewing and filtering
Use list for an activity-based view, list-detail for all task fields,
summary for counts and funding, and schedule for dependency readiness.
planner list-detail data/tasks.yaml
planner summary data/tasks.yaml
planner schedule data/tasks.yaml
Choose what to list
Use planner list KIND [task_file] [FIELD ...] to select the objects to display.
With TUXFAN_PLANNER_DATAFILE configured, omit task_file.
| Kind | Default contents |
|---|---|
tasks |
Existing activity-grouped task listing |
milestones |
Definitions, deadlines, outputs, associated tasks, direct links, and current required tasks |
deliverables |
Definitions, lifecycle status, producers, readiness, and required-by dates |
activities |
Every execution section, including empty sections, with tasks, counts, and funding; Unassigned appears when needed |
workitems |
Unique reference IDs with owners and every conflicting metadata variant |
risks |
Each risk entry with severity, mitigation, and owning task |
plan |
Plan metadata, execution overview/sections, and relationship summaries |
planner list tasks data/tasks.yaml
planner list deliverables data/tasks.yaml --only type=document
planner list deliverables data/tasks.yaml label status ready required_by
planner list milestones data/tasks.yaml --only deliverables=NEEDS
planner list activities data/tasks.yaml label task_count funding
planner list workitems data/tasks.yaml --only status=open
planner list risks data/tasks.yaml --only level=high
planner list plan data/tasks.yaml
planner list deliverables --help
Fields are scoped to the requested kind: list tasks ... status selects task
status only; list workitems ... status selects reference status. Identity
headings remain visible. Field names are exact, and each kind's help lists its
choices. Additional fields are tasks, direct_tasks, producer_tasks, and required_tasks for
milestones; producers, ready, and required_by for deliverables; tasks,
task_count, and funding for activities; tasks and derived type
(workitem/mr) for workitems; and tasks for risks.
These view fields do not extend the input schema or the show command.
Filters apply directly to the requested objects, so unreferenced definitions and
empty activities remain visible. Target a native field such as id, label,
type, status, or level, or related tasks, activities, sections, tags,
milestones, deliverables, or workitems. Relationship targets accept IDs or
labels (workitems use their IDs). Singular aliases work, and producers/producer
aliases tasks. Targeted values match whole values; bare values match literal
substrings. Matching ignores case and trims whitespace. Comma-separated values
are OR alternatives; repeated flags are AND requirements. For example:
planner list deliverables data/tasks.yaml --only type=document,paper --only status=complete
planner list deliverables data/tasks.yaml --only tasks=PURPOSE
planner list milestones data/tasks.yaml --only direct_tasks=PURPOSE
For tasks, --only id=ASSEMBLY selects every expanded part of multipart parent
ASSEMBLY; --only id=ASSEMBLY_A selects only that expanded task. Standalone IDs
still match exactly. Comparisons ignore case, but do not match prefixes or local
part IDs. Parent selectors can be combined with other filters, for example:
planner list tasks data/tasks.yaml --only id=AIRFRAME --only tags=build
Readiness always uses every producer in the full plan. Activity funding uses all
its tasks, counts multipart parent budgets once per activity, and includes
configured zero-funded years; years are inferred from funding if none are
configured. Milestone tasks retains historical links, direct_tasks shows direct links,
producer_tasks shows tasks required through outputs, and required_tasks
reflects current lifecycle requirements. Filtering does not change those values.
Shared workitem IDs appear once. Identical metadata merges owners; conflicting
labels, descriptions, statuses, or assignees remain in owner-labeled variants.
Repeated filters must match one variant. A selected reference still displays all
variants, so conflicts remain visible. Risks remain separate entries under their
owning tasks. All views share Markdown, links, 80-column wrapping, colors,
NO_COLOR, and automatic paging. IDs in identity headings and reference fields
use bold magenta so they stand out from labels and prose. Closed/unfunded entries
keep their gray color, with bold IDs. Plain and redirected automatic output
remain uncolored; --color always can explicitly enable the highlighting.
planner list plan.yaml and planner list plan.yaml FIELD ... preserve the legacy
task view, including its cross-context field selection and task filters. With a
default input, reserved kind names now select object views: planner list deliverables
lists definitions. Use planner list plan.yaml deliverables for the legacy
container projection. If a filename equals a kind, qualify it as ./tasks, etc.
The following task-list and filtering details describe the legacy shorthand;
list tasks without fields retains its task layout.
List output and ordering
Normal list output identifies each multipart group with an unnumbered parent
heading, such as Airframe Development [AIRFRAME]. Its parts are indented
beneath it, with their descriptions and details one level deeper. Filtering
retains the parent heading for matching parts. Part numbers and dependency
references stay the same. Field-selected output keeps its existing layout.
All divider lines end at column 82, including indented dividers between parts.
prints tasks in Word activity and task-number order with each task's description, a Note: line when present, numbered dependencies when present, status, and a single funding line for identified fiscal years (for example, Funding: $500K (FY27), $250K (FY28)). For configured fiscal years, a Total Funding: line at the bottom shows every year in thousands of dollars, including $0K years. Linked activity headings also show their execution section descriptions. Activity/task descriptions and notes wrap at 80 terminal columns, accounting for wide characters, combining marks, and styling. A gray block line separates tasks within an activity. Darker gray double rules align with activity headings before each activity and between its description and first task. It uses color when stdout is a compatible terminal, with dollar amounts in light green, statuses by state, and the entire entry for an unfunded or closed task in gray; --color always or --color never overrides automatic detection. NO_COLOR disables automatic color. Accepts a task file or uses TUXFAN_PLANNER_DATAFILE. Use field names such as label, status, or assignees to specialize output with nested context; combine them with --only to filter tasks first. label alone gives the compact label outline with work item ID fallback. Field selection omits funding totals.
prints the full task details in calculated end-month order, including the start and end fiscal periods and duration in months.
Paging long terminal output
Configure a pager once to keep colors without piping each command:
export TUXFAN_PLANNER_PAGER='less -R'
planner list
Long output opens in the pager automatically when both input and output are
terminals. Short output stays direct. Planner detects colors before opening
the pager, so --color always is unnecessary. NO_COLOR and --color never
still control styling. Redirecting or piping output bypasses automatic paging;
TERM=dumb also bypasses it. Unset the variable or set it to an empty value
to disable paging.
Paging applies to list, list-detail, summary, schedule, show, avail,
fields, and stdout help. Warnings/errors stay on stderr; validation output,
completion scripts, editing prompts, and export/transform messages stay direct.
The pager value is an executable plus arguments, with quoted paths supported,
and runs without a shell. If it cannot start, planner prints the output directly.
Output height accounts for wrapped lines and ignores ANSI color sequences.
Filter list output
Run planner list --help or planner list-detail --help for built-in filtering
examples, or see the CLI reference for detailed matching and
funding rules.
Use --only with list or list-detail to select tasks by activity,
execution-section ID, tag, or milestone ID/label:
planner list tasks.yaml --only tags="Tag1, Tag2"
planner list-detail tasks.yaml --only milestones="Flight Deliverables"
planner list tasks.yaml --only sections=Aircraft --only tags=gpu
planner list tasks.yaml label --only tags=gpu
planner list tasks.yaml --only "aircraft, gpu"
Use list FIELD to specialize output by any supported field identifier,
such as label, status, assignees, or mitigation. Replace FIELD
with the exact input field name. Combine field names to display several fields.
Nested selections retain the activity, task, and item context needed to identify
their values. Container names such as workitems show their complete contents.
Combine field selection with --only to filter tasks before displaying the
requested information. Run planner list --help for supported field names.
Shared names apply at each supported level: status selects task
and work item statuses. type selects task and risk types; work item types
are inferred and are not selectable input fields.
planner list tasks.yaml status assignees --only tags=gpu
planner list tasks.yaml risk mitigation
planner list tasks.yaml workitems
label alone retains the compact activity/task/work item outline, with two
spaces per level and work item IDs when labels are absent. Field names are exact canonical input
names (including underscores), without abbreviations, aliases, or computed
properties. Input composition directives such as defaults and parts are
expanded during loading, rather than exposed as selectable fields.
--only still filters tasks before rendering; work item labels/IDs and task
labels are not additional filter fields. Selected tasks keep their work items;
filtered metadata retains only associated milestone definitions and execution
sections. Selected output omits unrelated details, separator rules, generated
numbering, and funding totals. Empty requested fields display None; branches
without a matching field are omitted. See the CLI reference for
the full supported field list and contextual output examples.
A target= prefix limits matching to that field. Supported targets are
activities, sections, tags, milestones, and deliverables; singular names
also work. Activities match an activity name, section ID, or generated label
such as Activity B. Milestones match IDs or display labels. Targeted values
match complete field values, so tags=gpu does not match gpu-kernels.
Without a target, bare text matches substrings across all supported fields:
--only "aircraft" can match a milestone ID, its label, a project, or a tag that
contains aircraft. Matching ignores case and trims whitespace. Comma-separated
values within one flag are alternatives; repeated --only flags must all
match. For example, --only sections=Aircraft --only tags=gpu requires both the
project and the tag. Quote values containing spaces.
Only matching tasks and their associated activities are listed. With list --only,
activity headings show only IDs and labels, omitting activity descriptions.
Dependencies
are shown as references but do not pull other tasks into the view. Activity
letters, task numbers, and dependency numbers stay consistent with the full
plan. No matches produces a message and zero totals for configured years.
Unknown targets and empty value lists are usage errors.
Fiscal-year totals use the matching tasks. If a multipart parent has funding,
its full budget contributes once when any part matches, even when several parts
match or the parts specify their own funding. If the parent has no funding,
only matching parts' amounts contribute. list-detail also limits its activity
metadata and funding totals to the selection. Filtering does not change exports.
Discover field values and valid options
Field selectors use positional names throughout: list tasks.yaml label status,
show tasks.yaml tags, avail status, and fields task. The former --FIELD
selectors are no longer accepted. With a configured default data file, use
list label status or show tags. Options such as --only and --color retain
their usual syntax.
Use fields to see a mapping's supported keys and copy an example into a plan:
planner fields task
planner fields risk
planner fields workitems
planner fields plan > new-plan.yaml
Types are plan, task, workitem, risk, milestone, deliverable, execution, and
section; plural names tasks, workitems, milestones, deliverables, and sections are
also accepted, as is execution.sections. Output is plain YAML with example
values and comments listing fixed choices. Nested fields are expanded.
Examples are starter values, not schema defaults. Optional completion and
alternative fiscal-year fields are commented out. Individual mapping templates
need the containing key or list and appropriate indentation when pasted;
fields plan produces a complete plan. No input file is needed.
Print the tags used in a plan, or inspect the schema's allowed statuses:
planner show tasks.yaml tags
planner show tasks.yaml site
planner show tasks.yaml workitems.assignees
planner avail status
planner avail priority
planner avail level
Both commands require exactly one field name. Values print one per line;
avail status adds explanatory group headings.
show removes exact duplicates, skips empty values, and sorts alphabetically
while preserving spelling and case. It accepts scalar fields and lists of
scalars, including tags, dependencies, milestone references, and assignees.
Unqualified fields collect values from every applicable context; use qualified
names such as tasks.status or workitems.status to limit the context.
Structured containers such as risk, workitems, and funding are not
selectable. Includes and multipart inheritance follow normal plan loading.
No values means no output. The usual input environment variables apply.
avail needs no data file. status prints separate labeled groups explaining
the options for a task's status and a work item entry's status;
priority means task priorities, and level means risk levels.
Risk levels print in severity order: low, medium, high, extreme.
Priorities print in order: low, medium, high, urgent.
Task statuses are alphabetical with closed last; work item statuses print open, then closed.
Only status, priority, level, deliverables.type, and deliverables.status
are accepted by avail.
deliverables.type prints paper, document, presentation, release. Other qualified
field names are available with show; use it to discover free-form values.
Summary and dependency schedules
groups tasks by execution section and milestone and prints funding totals when task funding is present.
prints tasks in dependency order and marks them as READY, BLOCKED, ACTIVE, ONGOING, or COMPLETE.
Exporting
The output filename selects the format. export requires an options path from
--export-options or TUXFAN_PLANNER_EXPORT_OPTIONS; the following examples
configure the supplied sample. export-gantt does not use export options.
export TUXFAN_PLANNER_EXPORT_OPTIONS=planner/examples/export-options.yaml
planner export data/tasks.yaml /tmp/plan.docx
planner export data/tasks.yaml /tmp/plan.svg
planner export-gantt data/tasks.yaml /tmp/gantt.svg
planner export-gantt data/tasks.yaml /tmp/gantt.pptx
All Word, plan SVG, and Gantt SVG/PowerPoint exports include centered, bold
CUI//SP-BDGT headers and footers. Word repeats them on every page; PowerPoint
includes them on every slide.
Word and SVG plans
writes a Word plan for a .docx output path or a graphical plan for .svg. SVG plan export warns about empty or duplicate generated element IDs (including dependency-marker conflicts), identifies affected tasks, and still writes the output with unchanged IDs. Add --include-note or set include_note: true in export options to show an italic Note: line after each task description. Use --export-options PATH or TUXFAN_PLANNER_EXPORT_OPTIONS to control optional task attributes in both formats. The Word document includes a schedule and a detailed task table, starting on a new page with its section headings. When fiscal years are configured, the table includes one column per year with each task's funding level or a blank cell, plus a final total row. The SVG uses the same activity letters and task numbers as Word, and shows fiscal-year funding totals, completion years, and numbered dependencies. Its fill color reflects status, border color reflects risk, and an accent bar reflects priority. Both formats keep multipart task parts adjacent. Custom column labels and alignment apply only to Word.
Gantt charts
writes a fiscal-month Gantt chart as .svg or .pptx, selected by the output file extension. For ordinary tasks, bars span start through the end month calculated from expected. Ongoing tasks instead have separate full-year bars for each year with positive funding. By default, the axis covers the configured fiscal year range exactly; tasks outside it are omitted and overlapping bars are clipped. Without configured fiscal years, it covers task and completion dates. Optional inclusive --from and --through bounds override the corresponding axis endpoints and accept a fiscal year such as FY26 or an exact period such as M1Q1FY26; a fiscal year expands to its first or last month as appropriate. Rows follow execution activity order; each task row keeps its number and label on one line when they fit, otherwise wraps the label at a word boundary within the two-line cell. Arrows leave the dependency bar's right edge and enter the dependent bar's left edge, routing around overlaps without bending farther right than either bar requires; they connect bars within each activity, and PowerPoint draws an arrow when both bars appear on the same slide. Status colors and completion markers identify progress. The SVG is a vector image; the PowerPoint file uses editable native shapes and splits activities into slides of up to ten tasks, with additional slides for timelines longer than five fiscal years. Copy the desired slide into an existing presentation. Gantt exports do not use task table export options.
planner export-gantt data/tasks.yaml /tmp/fy27-fy28.svg --from FY27 --through FY28
planner export-gantt data/tasks.yaml /tmp/partial.pptx --from M1Q1FY27 --through M3Q2FY28
Inline formatting in exports
Word (.docx) and plan SVG (.svg) exports support a small inline Markdown
subset in displayed text fields, including labels, descriptions, summaries,
notes, milestone text, and optional table values:
description: "Deliver the **prototype**, review *performance*, and see [the report](https://example.com/report)."
note: 'Use __bold__ or _italic_ text; escape markers as \*literal asterisks\*.'
Use **bold** or __bold__, *italic* or _italic_, and
[link text](https://example.com). Bold and italics can be combined or nested.
Links accept http, https, and mailto URLs and remain clickable when text
wraps. Backslash escapes make marker characters literal; use single-quoted YAML
strings for these escapes, or double the backslash inside double-quoted YAML.
Unmatched markers and unsupported link targets remain literal text. Underscores
inside words and identifiers remain literal.
This is inline formatting only; headings, lists, images, code, and HTML markup
are not interpreted. Source values keep their original text. The list command
also interprets this subset in activity and task labels and descriptions, using
terminal bold/italic styles when color is enabled. Links display as label (URL).
Plain output removes formatting markers and retains link destinations; descriptions
wrap at 80 visible characters. Existing colors, including gray unfunded entries,
are preserved. Other CLI commands and export-gantt retain their original text.
Notes in exports still require
--include-note or include_note: true to appear.
Export options
Export options files can be YAML, YML, or Python. The supported settings are task_table_attributes, task_table_columns, and include_note. The first two control the optional task attribute columns included in the Word export summary table and the attributes shown on SVG task cards. Custom labels and alignment apply only to Word. The .docx table always starts with an unlabeled column containing generated task numbers; it does not include a Project column. An Activity A, Activity B, etc. row precedes each activity's tasks, which appear in numeric task order. When tasks link to execution sections, the activity row includes the section label and its letter follows section order (for example, Activity B: Specialization Work with Task B.1). Unlinked tasks appear together under Unassigned. Each activity label occupies one left-aligned cell spanning the table. The column header repeats only when the table continues onto another page; Activity rows appear at their normal group transitions. All table cells center their content vertically. Fiscal-year columns are added automatically when plan fiscal years are configured, with a final Total Funding row that counts parent budgets once when present, otherwise summing included part amounts. For completed tasks, those columns become one green-filled cell labeled with the completion year (for example, Completed FY26) when a completed period is available, or Completed otherwise; the other cells remain black on white. The optional task metadata columns are limited to the attributes listed here. Word task descriptions do not append parenthesized attributes or funding details.
Set include_note: true in an export options file, or pass --include-note to export, to show italic notes, including the Note: label, after task descriptions. Task note lines are hidden by default. Select note as a table attribute when you also want a Note column in the Word summary table.
In the Word risk mitigation section, the bold risk label is green for low, yellow for medium, orange for high, and deep red for extreme. Mitigation text remains black.
Top-level Word section labels, including Tasks:, are bold and underlined.
Supported attribute names:
bnrfundingnoteworkitemssitetypetags
Simple YAML:
task_table_attributes:
- site
- bnr
- tags
Shorthand YAML with custom labels:
task_table_attributes:
- bnr: BNR
- tags: Keywords
Recommended explicit YAML when you need labels or alignment:
task_table_columns:
- attribute: bnr
label: BNR
- attribute: tags
label: Keywords
Supported column alignment values:
leftcenterright
alignment is optional and defaults to center.
Example CLI usage:
planner export planner/examples/tasks.yaml /tmp/plan.docx --export-options planner/examples/export-options.yaml
Advanced plan authoring
These features help organize larger plans and represent recurring or multipart work.
Task defaults
One optional defaults entry inside the tasks list sets site, bnr, and
type for every task that omits them:
tasks:
- defaults:
site: Example Works
bnr: EXAMPLE-001
type: labor
- id: MAINTENANCE
label: Tool maintenance
description: Maintain the planning tool.
status: ongoing
funding: {fy27: 50K}
The three values must be indented beneath defaults. Only one defaults entry
is allowed, and it applies to all tasks regardless of its position. Explicit
task values override defaults; explicit null or empty values clear a default.
Multipart parents inherit defaults, and part values override parent values.
Without defaults, site, bnr, and type remain optional. This also works in
raw YAML lists and Python PLAN/TASKS lists. See
planner/examples/task-defaults.yaml.
Ongoing tasks and funding
For status: ongoing, start, expected, priority, and
risk are optional (dependencies and tags are optional for every task). Scheduling uses every fiscal year with
positive numeric funding for its full twelve months, even when start/duration
fields are supplied. Supplied optional fields are still validated. Omitted
priority defaults to low; dependencies and risks
default to empty lists.
id: Maintenance
label: Tool maintenance
project: Planning System
description: Maintain the planning tool.
status: ongoing
funding:
fy27: 50K
fy28: 0K
fy29: 50K
This task spans all of FY27 and FY29, with no bar in FY28. Ongoing work has one Gantt bar per funded year; gaps are preserved. Its duration is twelve months per funded year. Without positive funding, it remains in lists and schedules but has no Gantt bar. Ongoing tasks without funded years sort after dated tasks.
Multipart tasks
A task can also be a multi-part task by using parts instead of the per-task
schedule fields on the parent. Parent fields such as execution_section, site, bnr, note,
type and tags are inherited by each part, while each part
provides its own id, label, description, start, expected,
priority, status, dependencies, and
risk. Funding can be specified on the parent or on individual parts. Part ids are expanded as {parent_id}_{part_id}. Dependencies inside a
multi-part task can reference sibling part ids, and dependencies from other
tasks can reference the parent id to depend on all expanded parts. A parent-level budget contributes once to fiscal-year totals whenever any of
its parts is included. Without a parent budget, totals sum the included parts
only. Parts inherit parent funding unless they specify their own; explicit part
funding controls their displayed amounts and ongoing time spans, while totals
use the parent budget when present.
In exports, parts in the same activity stay together at the position of their
first part encountered in end-date order. Parts are ordered by end date, with
ties retaining declaration order in the parent's parts list. The list
command uses the same ordering, including
list label. Dependency-aware schedules still respect dependencies.
Merging and splitting tasks
Use merge and split to restructure YAML tasks without changing the input
file. Both accept a complete plan mapping or an incomplete task-list fragment,
including a file that another plan includes. Supply the input filename and a
new .yaml or .yml output filename explicitly:
planner merge tasks.yaml DraftDesign BuildPrototype --id Airframe --label "Airframe work" --output merged.yaml
planner split merged.yaml Airframe --output split.yaml
Merge accepts at least two standalone task IDs defined in the input file. It
puts the parent at the earliest selected task's position and preserves source
declaration order for the parts, regardless of command-line ID order. Identical
shared fields may move to the parent; differing values and funding stay on the
parts. Expanded IDs usually change (for example, DraftDesign becomes
Airframe_DraftDesign), and the command prints the ID mapping and rewrites
dependencies in the supplied file.
Dependencies between the merged parts retain short sibling IDs, such as
DraftDesign. References from other tasks use expanded IDs such as
Airframe_DraftDesign.
Split replaces a parent with its parts in declaration order, materializes inherited parent fields, retains expanded IDs, and replaces local dependencies on the parent with dependencies on all resulting tasks. If the parent has a funding field, choose a policy explicitly:
planner split tasks.yaml Airframe --funding parts --output split.yaml
planner split tasks.yaml Airframe --funding equal --output allocated.yaml
parts preserves each part's effective funding, including inherited amounts;
totals can increase when the original parent budget counted only once. equal
replaces part funding with equal shares of the parent budget, allocating any
remaining cents to the first parts in declaration order. Both commands report
local funding totals before and after where available.
Comments, quoted strings, block scalars, UTF-8 BOMs, and line-ending conventions
are retained where possible; YAML indentation may be normalized. Existing
outputs cannot be overwritten. !include directives stay external, with
relative paths adjusted if the output moves to another directory. Select tasks
in the file that defines them; included files are never edited. Python input
is not supported.
These commands check supplied task fields, visible ID collisions, and local
dependency cycles. They permit external dependencies and missing required
fields that may come from the containing plan. Review the ID mapping, update
references in other files, and run planner validate on the assembled plan
after replacing the fragment. Successful transformation means a structurally
valid fragment, not a fully validated standalone plan.
YAML includes and composite plans
YAML plans can be split across files with !include at any value position:
project: FY27 Plan
summary: !include prose/summary.yaml
milestones: !include milestones.yaml
execution:
sections:
- !include activities/solver.yaml
tasks:
- !include tasks/solver.yaml
- !include tasks/runtime.yaml
An included file contains the YAML value expected at that position: a mapping, list, or scalar. In a list, included lists are spliced in place; mappings and scalars become one item. Nested paths resolve relative to their containing file. Cycles and missing files are errors. Includes are value-only, with no implicit mapping merges; normal task validation follows expansion. Python plans and export-options files do not support includes.
Read commands load a temporary expanded snapshot and clean it up automatically. Write a standalone copy with:
planner composite plan.yaml expanded.yaml
# With TUXFAN_PLANNER_DATAFILE set:
planner composite expanded.yaml
The output argument is required. Output preserves data and ordering, including
defaults and multipart definitions, but not comments or formatting. It is written
atomically after expansion, without requiring task-schema validation, and cannot
overwrite any input file. format and spell-check reject composite plans before
tools, prompts, or changes. They can operate on individual fragments without
includes or on the standalone output. See composite documentation
for field-level examples and details.
Python format
Define PLAN or plan in a .py file for metadata plus tasks. The legacy TASKS or tasks list still works.
PLAN = {
"portfolio": "Advanced Simulation and Computing",
"project": "Task-Parallel Project",
"managers": ["Alice Example"],
"pocs": ["Casey Example, PI"],
"summary": "High-level planning context for the task collection.",
"fiscal_range_begin": 27,
"fiscal_range_end": 29,
"execution": {
"overview": "Overall execution context for the plan.",
"sections": [
{
"id": "deliverable_a",
"label": "Deliverable A",
"description": "Narrative execution detail for this deliverable.",
}
],
},
"deliverables": [
{"id": "ARCHITECTURE", "label": "Architecture document",
"description": "Reviewed architecture document.", "type": "paper"},
],
"milestones": [
{
"id": "Design",
"label": "Design",
"description": "Complete the architecture draft.",
"deadline": "M2Q3FY26",
"deliverables": ["ARCHITECTURE"],
}
],
"tasks": [
{
"id": "DraftArchitecture",
"label": "Draft architecture",
"bnr": "EXAMPLE-001",
"site": "Example Works",
"type": "labor",
"tags": ["architecture"],
"execution_section": "deliverable_a",
"description": "Produce the first architecture draft.",
"start": "M1Q3FY26",
"expected": 2,
"milestones": ["Design"],
"priority": "high",
"status": "complete",
"dependencies": [],
"risk": [
{
"type": "scope",
"level": "medium",
"mitigation": "Review the architecture with stakeholders before implementation starts.",
}
],
"funding": {"fy27": "50K", "fy29": "100K"},
}
],
}
Configuration and optional tools
Environment variables provide input and export defaults. Formatting, spell checking, and shell completion are optional conveniences.
Environment variables
If you set TUXFAN_PLANNER_DATAFILE, the CLI uses that file by default:
An empty value behaves as unset. Supply an explicit input filename in that case; omitting it produces the normal usage error (exit status 2).
export TUXFAN_PLANNER_DATAFILE=planner/examples/tasks.yaml
export TUXFAN_PLANNER_EXPORT_OPTIONS=planner/examples/export-options.yaml
planner validate
planner list
planner list-detail
planner export /tmp/plan.docx
planner export /tmp/plan.svg
planner export-gantt /tmp/gantt.pptx
Set TUXFAN_PLANNER_DATA_DIRECTORY to work with multiple files by filename:
export TUXFAN_PLANNER_DATA_DIRECTORY="$PWD/data"
planner validate tasks.yaml
planner list composite.yaml label
planner export tasks.yaml /tmp/airplane.docx
export TUXFAN_PLANNER_DATAFILE=tasks.yaml
planner validate
Relative input filenames use the configured directory first, including a relative
TUXFAN_PLANNER_DATAFILE. If the file is missing there, the same relative filename
is tried in the current directory. Existing invalid or unreadable inputs do not
trigger fallback. Absolute inputs
bypass the setting. Output and export-options paths are unchanged, and includes
remain relative to their containing files. The directory must exist; an empty
value acts as unset. Setting the directory alone does not choose a default file.
If you set TUXFAN_PLANNER_EXPORT_OPTIONS, the Word and SVG plan exports use that file by default:
export TUXFAN_PLANNER_EXPORT_OPTIONS=planner/examples/export-options.yaml
planner export planner/examples/tasks.yaml /tmp/plan.docx
export fails with exit status 1 if neither the environment variable nor
--export-options provides a non-empty path. Empty values are treated as unset.
A non-empty environment value takes precedence over the option, with a warning
when both paths are supplied. To use default export settings, provide a YAML
file containing {}. Relative options paths use the current directory.
Shell completion
The CLI can print completion scripts for bash, zsh, and fish:
planner completion bash
planner completion zsh
planner completion fish
For a one-session bash setup:
source <(planner completion bash)
The generated completion supports the basic planner subcommands, the
tuxfan-planner alias, file path completion for task and output arguments, and
--export-options for export commands. It also completes list/list-detail --only,
list field names such as label and assignees, and list --color values, plus spell-check --lang and --personal.
Formatting data files
Format a single data file in place, or use TUXFAN_PLANNER_DATAFILE:
planner format tasks.yaml
planner format tasks.py
planner format
YAML (.yaml/.yml) uses Google's
yamlfmt, installed separately from pip:
brew install yamlfmt
# Alternatively, with Go installed:
go install github.com/google/yamlfmt/cmd/yamlfmt@latest
Python (.py) uses Black from the same Python environment as planner:
python -m pip install 'tuxfan-planner[format]'
# In a checkout:
python -m pip install -e '.[format]'
An explicit path overrides the environment value. Only that file is formatted; Python inputs are never executed. The formatter runs from the data file's parent directory and uses its normal configuration discovery. YAML comments, quotes, anchors, and block strings are handled by yamlfmt. Source encoding and line-ending convention are retained. YAML structure and values are checked before saving; formatter failures leave the source untouched.
Changed files receive a numbered .bak backup and are replaced atomically.
Already formatted files are left alone. Missing formatter dependencies produce
an installation error; other commands remain available. This CLI command
formats data files; CMake's format target formats the planner source code.
Interactive spell checking
spell-check requires the Aspell executable and a language dictionary.
These are system dependencies, installed separately from pip:
brew install aspell # macOS / Homebrew
sudo apt install aspell aspell-en # Debian / Ubuntu
Check availability with aspell --version and aspell dicts. The default
language is en_US; select another installed dictionary with --lang.
planner spell-check tasks.yaml
planner spell-check # uses TUXFAN_PLANNER_DATAFILE
planner spell-check tasks.yaml --lang en_GB
planner spell-check tasks.yaml --personal /path/to/project-words.pws
The terminal prompts show the filename, field, line, context, and numbered
suggestions. Choose a suggestion number, r for a manual replacement, i to
ignore once, a to ignore that spelling for the session, d to add it to the
personal dictionary, or q to cancel. At the end, review the change summary
and answer the save prompt. The default answer discards changes. Quitting,
Ctrl-C, or end-of-input before saving discards staged corrections and dictionary
additions. Interactive terminal input is required.
Spelling checks cover prose: plan/project names, managers/contacts, summaries, execution narratives, task and milestone labels/descriptions, notes, deliverable labels/descriptions, risk descriptions/mitigations/types, and task site/type/tags. Schema keys, IDs/references, fiscal periods, status/priority/risk-level values, funding, and Markdown link destinations are skipped. Original source strings are checked once, including inherited multipart text and YAML aliases. Aliases or Python literals shared with structural fields require manual review. Notes are checked regardless of export visibility. Files need valid syntax but do not need to pass task validation.
Accepted corrections preserve source comments, quoting, block styles,
indentation, line endings, and encoding. Saving creates a .bak backup
(.bak.1, .bak.2, etc. if earlier backups exist) and atomically replaces the
source after syntax checks. Concurrent source changes stop saving; symbolic
links require running on the resolved target. Python inputs are inspected
without execution. Ordinary and triple-quoted literal strings can be edited;
computed values, raw strings, and concatenated literals receive manual-review
messages. Escaped spellings that cannot be replaced without changing syntax
also require manual editing. Dictionary additions use Aspell's standard personal
dictionary or the path specified by --personal and are saved only after the
final prompt. Other planner commands work without Aspell.
Troubleshooting and further documentation
Ill-formed commands print an error and the relevant help text to stderr, then
exit with status 2. Use planner COMMAND --help to check accepted arguments.
Input-file warnings and errors show filename:line when available. Funding
warnings identify the funding entry; task validation errors identify the task
block. Line numbers also cover literal Python inputs and YAML/Python syntax
errors. Computed Python task entries may only have a filename.
Validation
checks required fields, invalid status values, invalid fiscal periods or non-positive/non-integer expected durations, invalid ids, duplicate ids, missing dependencies, and dependency cycles. Prints PASS/FAIL and statistics instead of plan metadata: activities (using list/export grouping), expanded tasks, milestone and deliverable definitions, execution sections, configured fiscal years, work item references per task, and emitted warnings. Warnings appear on stderr with source locations and terminal styling and are also counted; failures retain error diagnostics on stderr.
Migrating older plans
For existing task files, rename expected duration or expected_duration to
expected and remove the task deadline field. Milestone definitions still use
deadline.
Replace the former task milestone field with a milestones list. Legacy
milestone names must become IDs with top-level definitions.
The former list --labels flag has been replaced by list label.
Documentation
Sphinx documentation lives in docs/. See the
developer setup and checks for the current dependency and HTML
build commands.
The repository's Documentation workflow is defined in
.github/workflows/docs.yml. It builds the Sphinx output and publishes it to
the gh-pages branch.
Updating the virtual environment
Follow the CMake workflow or the
direct dependency commands in
the developer guide to update the root .venv and check the result.
After configuring CMake, the default build performs an editable install:
cmake -S . -B build
cmake --build build
# Equivalently, from inside build/:
cmake --build . --target install-editable
The target uses the absolute source directory, so it works from any build location. Dependency upgrades and development checks remain explicit targets.
Metadata
Release files for tuxfan-planner 0.2.23
For a detailed explanation of source distributions (sdists) and built distributions (wheels), please see the package formats documentation.
Source distribution (sdist)
| File | Size | Uploaded | Provenance | Actions |
|---|---|---|---|---|
| tuxfan_planner-0.2.23.tar.gz | 232.3 kB | Without provenance | Details for tuxfan_planner-0.2.23.tar.gz |
Built distribution (wheel)
| File | Interpreter | ABI | Platform | Actions Reset |
|---|---|---|---|---|
| tuxfan_planner-0.2.23-py3-none-any.whl | Python 3 | none | any | Details for tuxfan_planner-0.2.23-py3-none-any.whl |
Total release size: 344.3 kB
Release files / tuxfan_planner-0.2.23.tar.gz
| Download URL | tuxfan_planner-0.2.23.tar.gz |
|---|---|
| Size | 232.3 kB |
| Tags | Source |
|
SHA-256 checksum How to use checksums |
156b7dd6374315b111d2c7c7d7061cbf6eb9e3a012821e12506bfcd561ec53d3
|
|
BLAKE2b-256 checksum How to use checksums |
be33581017f33d2996a6b5dfb9b139956f74b9979ffb47c784ef1e336c22af9e
|
| Upload date | |
|
Uploaded using Trusted Publishing? What is trusted publishing? |
No |
| Uploaded via |
twine/7.0.0 CPython/3.15.0
|
Release files / tuxfan_planner-0.2.23-py3-none-any.whl
| Download URL | tuxfan_planner-0.2.23-py3-none-any.whl |
|---|---|
| Size | 112.1 kB |
| Tags | Python 3 |
|
SHA-256 checksum How to use checksums |
97d3c3d3da4d35293e981d3856f72cca4e941e9d772c99aad107ee0372c7c8d2
|
|
BLAKE2b-256 checksum How to use checksums |
396741e935edb36afead759dd0b85ea61bccde8e9b2f9d083ae51633997876ad
|
| Upload date | |
|
Uploaded using Trusted Publishing? What is trusted publishing? |
No |
| Uploaded via |
twine/7.0.0 CPython/3.15.0
|
Security for tuxfan-planner 0.2.23
Provenance
Provenance describes where a file came from. On PyPI, provenance is shared via attestations, which provide a verifiable record of the build or publishing details. View details, limitations and caveats.
No provenance found
None of the files in this release were uploaded with provenance metadata.
A note on package security